a breakdown of the CommBuys project timeline phase 1-3 by date
Fall 2012
  • eProcurement Solicitation Posted
  • 4 Bidders Responded
Spring 2013
  • Announced Apparent Successful Bidder
  • Contract Negotiations Finalized
Summer/Fall 2013
  • Phase 1 Begins: Implementation of a state-of-the-art online procurement system
  • Project Team Ramp Up
  • Requirements Gathering
Winter 2013/Spring 2014
  • User Acceptance Testing
  • User Readiness & Implementation Activities
  • COMMBUYS goes live March 24th with online catalogs and bid management
  • Comm-PASS Retired
Fall 2014/Winter 2015
  • Phases 2 & 3 Begin: COMMBUYS Interface to the Massachusetts Management Accounting and Reporting System (MMARS) for Full Financial Procure-to-Pay Cycle
  • User Readiness & Implementation Activities
  • Development of Business Analytics and Reports
  • SBPP Validation Process
Spring 2015
  • COMMBUYS Interface to MMARS goes Live
  • Full Procurement-to-pay Lifecycle Available
  • Ad Hoc and Pre-Defined Reports Available for Spending and Other Analysis

Recommended Content

People also viewed...

You recently viewed...

Personalization is OFF. Your personal browsing history at Mass.gov is not visible because your personalization is turned off. To view your history, turn your personalization on.

Learn more on our .

*Recommendations are based on site visitor traffic patterns and are not endorsements of that content.