Study & Project Designer: Leers Weinzapfel
Contractor: Daniel O'Connell Sons
Project Type: CM at-Risk
Project Cost: $80 million
Gross Square Feet: 147,114
Construction start: October 2008
Substantial Completion Date: May
2011


Construction of the new Taunton Trial Court is now complete. The courthouse contains eight courtrooms serving the District Court, Juvenile Court, Housing Court, and Probate & Family Court. Together with the Superior Court building, the complex will serve as a comprehensive justice center for Northern Bristol County.

Project Features

  • Eight courtrooms
  • Close proximity to the existing Superior Court building
  • LEED GOLD Certified