Framingham State University

Contractor: BG Mechanical Contractors, Inc.
Cost: $15 million
Estimated Substantial Completion:
Phase I - November 2011
Phase II - September 2012
 

Project Details:

Comprehensive energy and water saving performance contract. Expected to include, among other measures, a boiler plant upgrade, the installation of energy management controls, and lighting and water upgrades.

Project Highlights:

  • Comprehensive lighting and lighting controls retrofit
  • Boiler replacement
  • Re-commission and expand existing EMS controls
  • Ad central BMS controlsSignificant HVAC replacements and mechanical upgrades
  • Water conservation retrofits
  • Chiller replacement
  • Solar PVs