Designer -The Architects Forum
Contractor - Groom Construction
Project Type: Design/Bid/Build
Project Cost: $11 Million
Gross Square Feet: 185,000
Completion Date: July 2007
This construction project consisted of fire protection improvements, the addition of a central air conditioning system and the replacement of the medical gas systems in the Quigley Building at Chelsea Soldiers' Home. It was a multiple-phase life safety project.
Project Features
- New fire protection and central air conditioning system with ancillary electrical, heating and plumbing upgrades and asbestos abatement.
- Replacement of medical gas systems