Chelsea Soldiers' Home

Designer -The Architects Forum
Contractor - Groom Construction
Project Type: Design/Bid/Build
Project Cost: $11 Million
Gross Square Feet: 185,000
Completion Date: July 2007

 

This construction project consisted of fire protection improvements, the addition of a central air conditioning system and the replacement of the medical gas systems in the Quigley Building at Chelsea Soldiers' Home. It was a multiple-phase life safety project.

Project Features

  • New fire protection and central air conditioning system with ancillary electrical, heating and plumbing upgrades and asbestos abatement.
  • Replacement of medical gas systems