Fire Detection McCormack Building -UPDATED Installation
schedule
UPDATE
10/ 5
Agency
Construction Schedule:
Sept
25-27th - 14th floor Completed
Sept
28,29 - 12 th floor Completed
Oct 2-4
- 13 th floor Completed
Oct 4-6
- 10th floor Ongoing
Oct 9 -
3rd shift work only in garage
Oct
10,11th - 9th floor Scheduled and confirmed by BSB - no change in date
Oct
12,13th - 8th floor Scheduled and confirmed by BSB - no change in date
Oct
16-18th - 5th floor - Scheduled Confirmed by BSB
Oct
18th -20th - 6 th floor Scheduled for 10/18-20th Confirmed by BSB
Oct
23-25 - 11 th floor - Scheduled and confirmed by BSB ***** MOVA
Oct
25-27th - 3rd floor confirmed by BSB
Oct
30,31 - 4th floor - Scheduled and confirmed by BSB
Nov 1-3
2nd floor confirmed by BSB
Nov 6-8
1st floor -to be scheduled for walkthrough
Nov
9,10 PLAZA -to be scheduled for walkthrough
NOV
13-17 Installation of additional devices throughout building and SIMPLEX
TESTING?