The Official Website of the Division of Capital Asset Management (DCAM)

Division of Capital Asset Management (DCAM)



spacer
spacer
energy
Sustainable Design
Energy Conservation News and Events
Energy and Water Conservation Program
Performance Contracting Program
Bond-Funded Projects Audits/Audit Updates
Utility Partnerships
Program Highlights
Performance Contracting Project Snapshots
spacer
spacer
spacer
spacer
spacer
spacer
spacer
spacer
DSB:  Designer Selection Board
spacer

spacer

ENERGY and SUSTAINABILITY
Performance Contracting Project Snapshots


Performance Contracting Project Snapshots

MMA wind turbine

Mass Maritime Academy
(completed June 2006)


Renewable energy project - 660 kW Wind Turbine
Project cost - $1.34 million including $500,000 grant from Mass Technology Collaborative
Project savings - $225,000 annual savings and 1.4 million kWh (about 25% of MMA’s electrical use)

Bridgewater State College
BridgewaterStColl (In construction)

Comprehensive energy and water savings project

  • High efficiency lighting
  • High efficiency motors
  • Energy management system upgrades
  • Replacement of steam traps
  • Domestic water conservation
  • Installation of variable frequency drives
  • New boiler controls at central plant

Project costs - $10.4 million (non capital funds)
Project savings - $956,000 guaranteed annual savings

DOC Norfolk/Walpole Correctional Complex
Walpole DOC(In construction)

Comprehensive energy and water savings project

  • Energy efficient low-pressure steam boilers and cogeneration equipment
  • Energy efficient lighting and controls
  • Enhanced energy management systems
  • Steam system upgrades
  • Water conservation

Project cost - $18.18 million (non capital funds)
Project savings - $1.52 million guaranteed annual savings

UMass Amherst
UMassAmherst (In construction)

Comprehensive energy and water saving project

  • Energy efficient lighting and controls
  • Steam system upgrades
  • New back pressure steam turbine
  • New chiller upgrades
  • Domestic and power plant water conservation
  • Enhanced energy management system controls
  • High efficiency motors
  • Campus fume hood controls

Project cost - $42.7 million (non capital funds)
Project savings - $5.3 million guaranteed annual savings