The Official Website of the Division of Capital Asset Management (DCAM)

Division of Capital Asset Management (DCAM)




Spacer
Spacer
Spacer
Spacer
Designer Selection Board
Designer Evaluation Forms
Construction- Bidding
Contractor Certification Instructions
Financial Issues
Debarment List
Spacer
Spacer
Spacer
Spacer
Spacer
Spacer
DSB:  Designer Selection Board
Spacer


spacer

Doing Business with DCAM
Designer Evaluation Forms


Designer Evaluation Forms

In collaboration with the Designer Selection Board, the Division of Capital Asset Management has developed the Standard Designer Evaluation Form for all Public Agencies. As part of the Construction Reform Legislation passed this year, Section 13 of Chapter 159 of the Acts of 2000 amends Section 38E of MGL Chapter 7 to require all Public Agencies receiving funding for building construction through the Commonwealth to complete Designer Evaluations.

If you are working on a project with a Public Agency exclusive of the Division of Capital Asset Management, please refer to Designer Evaluations for Public Agencies Web Page.

The intent of these evaluation forms is to improve accountability among the Designers and the Public Agencies they serve. The information on these evaluations will be made available to the Designer Selection Board and to the Public Agencies to assist them as they select design firms for public building projects.

At the completion of the project stages of Study Program Submission(S3), Study Completion (S10), Schematic Design (B1), Design Development (B4), Construction Documents (C9), 60% of Construction (D60) and Construction Substantial Completion (E-1), the Project Manager (PM) will complete evaluation forms.

At the initiation of a project, all project managers should provide a copy of the evaluation forms to Designers (they will be incorporated into Form 9) and note that they will be evaluated according to the categories noted on the forms. Design/Build projects will not require a Designer Evaluation as the Division does not hold a contract with the Designer for these projects. Designer Evaluations must be completed for all projects that are currently contracted, but not yet completed. At the next relevant milestone of the project (as noted above) PM's must complete the Designer Evaluation form.

You can download the forms as Microsoft Word 97 Documents, by clicking the appropriate link:

If you wish to download an Acrobat Adobe PDF version of either form, click the appropriate link:

The PM is responsible for completing and signing the evaluation forms and obtaining input from all relevant parties and reviewers at the completion of each stage. Any member of DCAM staff who worked directly with the designers should be consulted to ensure that the evaluation is reflective of their performance on all aspects of the project. The evaluation should be independent and fair, based only on the specific project for which the evaluation is being completed. Each form must be reviewed and initialed by the appropriate supervisor: Deputy Director of Construction Services as well as the Deputy Commissioner; or the Director of Programming (depending on the stage). Any changes to the evaluation must be recorded in the database so that the signed hard copy maintained in the file is the same as that in the database.

The Designer will have the opportunity to submit a written response to DCAM and to the Designer Selection Board disputing any information contained in the form and setting forth any additional information concerning the building project or the oversight of the building construction contract by the DCAM as may be relevant to the evaluation of the designer's performance on the contract. Any such letter must be attached to the evaluation form for inclusion in the designer's file. The Database will indicate that a Designer's reply has been received, but a copy of the reply will be stored only as hard copy in the Designer's file at DCAM and with the Designer Selection Board.

The completed Evaluation forms from the Final stage of the Project and any Designer's reply must be maintained as hard copy in the project file and forwarded by the PM to the Designer Selection Board for inclusion in the Designer's Qualification File. The Final stages are defined as follows: Study Final Completion (S10) for Study, Construction Documents (C9) for Design, Construction Substantial Completion (E1) for Construction.

To encourage constructive and productive feedback to designers, the legislature provided for certain protections for public employees completing these evaluations. DCAM encourages all managers, as well as firms doing public design and construction, to take full advantage of this communication tool. This is a great opportunity to enhance our ability to provide the best services to the public sector.

Please feel free to email Designer.Evaluations@state.ma.us with any questions you may have regarding the Evaluation Forms.