Construction
Management Options for Tunnel Rehabilitation:
1. Full closure of
·
Estimated cost: $40 million
·
Estimated project duration: 18 months
·
Anticipated traffic impacts: All
traffic will be detoured onto
·
Anticipated times of heavy construction activity: 7:30
a.m.-7 p.m.
·
Estimated area of Esplanade closed to public during
construction: Approximately 1200
feet by 40 feet adjacent to the edge of the pavement from the
·
Total tree loss on the Esplanade and Back Street: 22 trees
2. Construct a temporary eastbound bypass road along Back Street and route daytime westbound traffic through the existing tunnel, with nighttime westbound shut down
·
Estimated cost: $40 million
·
Estimated project duration: 29 months
·
Anticipated traffic impacts: Daytime,
approximately 80 percent of traffic flow will be maintained; the remainder will
be detoured onto local streets. At night, because of the full closure of the
tunnel, westbound traffic will be detoured onto local streets.
·
Anticipated times of heavy construction activity: 9 p.m.-6
a.m.
·
Estimated area of Esplanade closed to public during
construction: Approximately 1200 feet by 40 feet adjacent to the edge of
the pavement from the
·
Total tree loss on the Esplanade and Back Street: 70 trees
3. Construct a temporary eastbound bypass parallel to Back Street and a temporary westbound bypass road along the southern edge of the Esplanade.
·
Estimated cost: $50 million
·
Estimated project duration: 22 months
·
Anticipated traffic impacts:
Approximately 80 percent of traffic flow will be maintained; the remainder will
be displaced onto local streets.
·
Anticipated times of heavy construction activity: 7:30
a.m.-7 p.m.
·
Estimated area of Esplanade closed to public during
construction: Approximately 1200-foot
by 40-foot area adjacent to edge of pavement starting at the Fiedler Footbridge
to Clarendon Street to accommodate a temporary westbound bypass detour.
·
Total tree loss on the Esplanade and Back Street: 89 trees
4. Construct an elevated parkway detour
·
Estimated cost: $65 million
·
Estimated project duration: 34 months
·
Anticipated traffic impacts: A full
closure of westbound traffic for three weeks while the elevated roadway is
constructed. Once it is constructed, 80 percent of traffic flow will be maintained; the remainder
will be displaced onto local streets.
·
Anticipated times of heavy construction activity: 7:30
a.m.-7 p.m.
·
Estimated area of Esplanade closed to public during
construction: Approximately 1600-foot
by 40-foot area adjacent to edge of pavement from the Hatch Shell to