Completed Three Cornered Pond Road Area
Completed Three Cornered Pond Road Area

Status – June 26, 2014

Due to low market demand for red pine products in the summer months the Pine Barrens Restoration Timber Harvest is temporarily on hold.  Cutting operations will begin again sometime in late fall/ early winter.  To date, approximately 147 acres have been cut, representing 30% of the project.  Check back in the fall for an update on the resumption of cutting operations.

Status – June 6, 2014

Cutting is complete in the plantations along Mast Road, but trucks will still be loading material.  The contractor is cutting along East Line Road between Priscilla Road and Three Cornered Pond Road.  He will proceed to Three Cornered Pond Road, just west of Bare Hill Road.  Liggett Road, East Line Road, Priscilla Road, and Three Cornered Pond Road, along with paved bike paths in the immediate area, are temporarily closed. Expect traffic delays along Mast Road and Bare Hill Road.

Please obey the signs for your own safety.  Do not approach any machinery or equipment.

Status – May 2, 2014

Cutting is complete in the College Pond Recreational Area.  The contractor will be cutting along Priscilla Road and East line Road.  Liggett Road, Priscilla Road, East Line Road and Three Cornered Pond Road will be temporarily closed.  Bike paths in the immediate area, are temporarily closed.  Expect traffic delays along Alden Road and Upper College Road.

Please obey the signs for your own safety.  Do not approach any machinery or equipment.

STATUS – APRIL 9, 2014

Harvesting of the red pine is in full swing now.  The contractor will finish cutting just south of Three Cornered Pond Road and east of Bare Hill Road in which the bike path passes through.  He will proceed across Bare Hill Road to cut a small strip along Bare Hill Road as well as a small plantation at the intersection of Bare Hill Road and Musquash Road.  He will then proceed to a small plantation along the eastern side of Bare Hill Road between Federal Pond Road and Three Cornered Pond Road.  He will proceed to a plantation bounded by Ebeeme Road, Bare Hill Road and Three Cornered Pond Road.  Musquash Road, Ebeeme Road, and Three Cornered Pond Road, along with paved bike paths in the immediate area, are temporarily closed.  Expect traffic delays along Bare Hill Road.  

Please obey the signs for your own safety.  Do not approach any machinery or equipment.

Timber Harvest status

STATUS - APRIL 1, 2014

The contractor will be cutting at the intersection of Lower College Pond Road and Halfway Pond Road, and the intersection of Lower College Pond Road and Bare Hill Road.  He will proceed to the red pine plantation just south of Three Cornered Pond Road and east of Bare Hill Road in which the bike path passes through.  Lower College Pond Road, north of Halfway Pond Road, as well as the paved bike path in the immediate area are temporarily closed. Expect traffic delays along Halfway Pond Road, Lower College Pond Road, and Bare Hill Road.

Please obey the signs for your own safety.  Do not approach any machinery or equipment.

STATUS - FEBRUARY 11, 2014

The red pine has been sold, and harvesting should begin sometime in early March.  Check back for updates on the progress of the sale and areas closed for public safety.

Timber Harvest


Overview

There are approximately 576 acres of planted red pine (Pinus resinosa) stands located throughout Myles Standish State Forest .  Many of these plantations were planted after large wildfires.  The largest section of red pine plantations occur in the western portion of the forest, which was planted after the 1957 fire.  Norway spruce was also planted alongside red pine in a few instances.  Small rows of red pine are located along paved roads, forest roads, hiking trails, or paved bike paths.  


The majority of the red pine in Myles Standish State Forest are showing signs of infestation by red pine scale, (Matsucoccus resinosae) and of diplodia blight (Diplodia pinea).  Outward signs of the combined insect and fungus attack are discolored and brown needles and, in some plantations, complete tree mortality.  In some cases, these two biological agents have killed entire red pine plantations/stands.  Many of the plantations are declining rapidly, going from no noticeable decline to dying in a matter of less than two years.  


Objectives

The objective of the timber harvest is to complete an ecological restoration by allowing native vegetation communities of pitch pine and scrub oak, or Pine Barrens pdf format of Pitch Pine/Scrub Oak Communities to flourish and provide habitat for a diversity of endangered species.  Many plantations were established on former pine barrens habitat or are adjacent to existing pine barrens.  The project will protect and enhance public safety through the removal of red pine trees along roads, forest roads, hiking trails and paved bike paths.  The project also will reduce wildfire danger and provide safe access to firefighters and fire apparatus.  Non-native plantation removal is a high priority for pine barrens management in DCR's 2011 resource management plan. The project will remove approximately 500 acres of red pine plantations within Myles Standish State Forest. Harvest Map pdf format of MSSF-RP-harvestmap


Forest Roads, Trails, and Paved Bike Paths

Several paved roads, forest roads, hiking trails, paved bike paths, and illegal trails are abutting or located within the project area.  Signs will be displayed to close the project area during timber harvesting operations.  Legal trails will be reestablished once the project is completed.  Given the objective of enhancing public safety, no road or trail buffers will be retained so as to reduce the future risk of injury from falling dead trees or limbs.


Aesthetics

As whole tree removal and large clearing will occur, the resulting landscape will have a dramatic change in appearance.  The removal of the trees will reduce the fuel load and any hazardous trees to minimize the risk to public safety.  It is expected that only a small amount of slash will remain on-site as the trees are removed.  Visuals in the trail areas where harvest occurs will change from a forest canopy to an open shrubland savannah.    Because red pines will be removed to promote native species of pitch pine, scrub oak, and shrubland species, the landscape view will change from a single species monoculture to a more diverse, multi-structured forest.

Pre-harvest
Pre-harvest
Immediate post-harvest
Immediate post-harvest

Red Pine Scale

Red Pine Scale

Red pine scale is found throughout New England, New York, New Jersey, and eastern Pennsylvania.  It was first reported in Connecticut in 1946 and was most likely introduced to the United States on exotic pines planted at the New York World’s Fair in 1939.  Over the past few years it has spread across most of MA.  The first visible signs of infestation include discoloration of the lower branches, followed by swift decline of the entire crown and rapid stand wide mortality.  Red pine scale is a flightless insect that is spread by birds, squirrels, and the wind.  The insects are not visible to the naked eye, but the females secrete a white, fuzzy protective covering called “flocculent”, which helps insulate the insect over the winter; it is the most visible sign of the insect infestation.  The insects pierce the phloem of the bark and suck the moisture from the trees stressing them as if there was a drought.  Once stressed, the trees are susceptible to secondary pests such as the Turpentine Beetle or the Whitespotted Pine Sawyer, which bore into the main stem causing additional stress and introduce other pathogens.


Rare and Endangered Species and Wildlife

Buck moth

Most of the Myles Standish State Forest is within the Natural Heritage Endangered Species Program (NHESP) priority habitats of rare species.  The pitch pine-scrub oak barrens within MSSF provide habitat for a diversity of state-listed animals and plants, including 15 species of moths and butterflies, two tiger beetle species, and three species of plants.  Most of these barrens species rely on habitat with an open vegetation structure, such as scrub oak shrublands and heathlands. A few of the “barrens” species prefer even more open habitat, perhaps more accurately described as savanna or sandplain grassland.  Per the 2007 Biodiversity of Myles Standish State Forest report from NHESP, plantation removal of non-native species is the highest priority recommendation for pine barrens management.  


Vegetation Management in Reserves

Whereas habitat manipulation, silvicultural treatments, and commercial harvesting operations are not typically permitted in Reserves, from page 20 of the Landscape Designations for DCR Parks & Forests: Selection Criteria and Management Guidelines “… some situations may call for ecological restoration and vegetation management.  Situations where some management may be appropriate include the removal of invasive species or for the protection of existing rare species. Fire adapted Reserves in Southeastern Massachusetts may require active restoration and management to maintain habitat for rare species and reduce the risk of catastrophic wildfire that can threaten human health and safety.”


Project Timeline

The timber harvest project will begin sometime in late February 2014.  Mechanical equipment may include a feller-buncher which cuts and stacks the trees, a grapple skidder that pulls the trees to the landing, and a chipper that processes the trees into chips, which are then blown into trucks.

Feller Buncher
Feller Buncher
Grapple skidder
Grapple skidder

After Removal of the Red Pines

After Pine Removal

Future silvicultural treatments will be prescribed burning, mowing, and a combination thereof to kill white pines that typically establish in such areas and to stimulate sprouting and growth of native shrubs.  Active management using these methods will be planned in coordination with the NHESP, and done at variable frequencies and intensities to encourage a mosaic of pine barrens, shrublands, and woodland communities.  


In the absence of disturbance, fire or mechanical, the vegetation components will rapidly move through succession, particularly the understory of scrub oak, huckleberry and blueberry.  Where white pine is present, it may compete with pitch pine for growing space and eventually, after many years, dominate the site.  This would be an undesirable condition, as the objective of this project is to return the rare Pine Barrens habitat and maintain it to provide for the rare flora and fauna that exist within it.


History of Plantations at Myles Standish State Forest

As a result of colonial wood utilization and wildfires, most of the original forest was cleared and burnt over by the mid-1800s. The Massachusetts Game Sanctuary Association initiated reforestation efforts in 1912 by planting 30,000 white pines around Barrett Pond and East Head Reservoir.  In 1916, the State Forest Commission purchased the 5,700-acre Game Sanctuary Association property, creating Myles Standish State Forest (MSSF).  By the end of the 1920s, the state had purchased the majority of the land we now know as MSSF.  Today, MSSF has approximately 12,404 acres and is the largest public recreation area in southeastern Massachusetts.  


After acquiring the land, the state continued the reforestation program over the next 40 years. With the help of state unemployed crews and Civilian Conservation Corps crews in the 1930s, approximately 1.9 million white, red, Austrian, jack and Scots pines, spruce, and other species were planted in the forest between 1916 and 1937.  After the 1957 fire, several stands of red pine, white pine and Norway spruce were planted in the western portion of MSSF in an effort to reforest the area.

For additional information regarding the Pine Barrens Restoration timber harvest at Myles Standish State Forest, contact DCR Management Forester Paul Gregory at (508) 866-2580 ext. 121.