winthrop beach

The Massachusetts Department of Conservation and Recreation (DCR) is in the midst of undertaking a $25 million dollar renourishment and restoration project at Winthrop Beach. As anyone who watches TV news weather reports knows, during major storms, Winthrop Beach is routinely subject to overtopping of the seawall and major flooding of Winthrop Shore Drive and surrounding roads and properties. DCR’s much-needed shore protection project is designed to better fortify Winthrop Beach against the full force of northeast storms and natural beach erosion. The nourishment will also result in an expanded beach area for recreational use. 

 
The project is broken into four phases of work. The first two phases of the project – groin repairs and nourishing the southern end of the beach – were completed in 2013.  Phase 3 of the project, about to get underway, involves trucking in sand from a borrow site in Rumney Marsh in Saugus to nourish the northern end of the beach. The fourth phase of the project will include improvements to Winthrop Shore Drive.


The Winthrop Beach Renourishment Project compliments a separate project by expanding a planned salt marsh restoration at DCR’s Rumney Marsh Reservation in Saugus.   The subsequent project for Rumney Marsh is currently in design and received a funding boost by its connection to the Winthrop project. The Ballard Street Marsh Restoration will be undergoing a public review process with a public meeting this spring.  Work should commence by the summer of 2015.    

Winthrop Beach Nourishment Project

Two Week Look Ahead

November 24, 2014 - December 5, 2014

Work is winding down before winter. The following items will be occurring over the next two weeks.

Saugus

Excavation of material from embankment

Winthrop Beach

Build Groin #6
Delivery and spreading of beach material

 

Winthrop Beach 2 week                        Rumney Marsh Restoration

Please be advised that the Contractor will be shutting down for the winter in approximately 4 weeks.

In Winthrop, all material will be placed on the beach and construction of the terminal groin will be complete prior to shutdown. The fence will remain in place through the winter. All seawall openings will be closed off with temporary blocks at a height equal to or higher than the existing seawall. The Contractor will return in the Spring to assess beach material movement, possibly deposit more sand if necessary, and finalize work on the seawall and Pearl Avenue.
In Saugus, the Contractor will be done with Phase 1excavation in approximately 4 weeks. At that time, the site will be closed off and all equipment will be removed from Rumney Marsh. The Contractor will return in the Spring to install the footpath and all plantings along the berm left in place.

Throughout the winter, Steve Colometo will still be reachable at the below phone number for questions and concerns.
Questions or concerns about the project should be directed to DCR Resident Engineer Steve Colometo, at the DCR trailer behind the DCR bathhouse on Winthrop Shore Drive, by visit or phone (617-539-4957) during regular business hours,  Monday through Friday from 7 a.m. – 3:30 p.m.   In case of an emergency, contact 911 or DCR’s 24/7 emergency hotline at the Massachusetts Emergency Management Agency at 508-820-1428.   

Project Schedule

Winter/Spring 2014

  • Crest Avenue parking lot expansion and improvements
  • Mobilization in Winthrop and Saugus
  • Revetment work at Pearl Avenue
  • Groin repairs at Winthrop Beach
  • Beginning of sand extraction in Saugus and placement at Winthrop Beach

Summer 2014

  • Construction of Terminal Groin at Winthrop Beach
  • Continued extraction of sand in Saugus and  placement at Winthrop Beach

Fall 2014

  • Construction of footbridge and Ballard Street parking lot improvements in Saugus
  • Repair of Hawthorn Avenue Ramp  in Winthrop
  • Restoration of Cutler Street entrance at Winthrop Beach

Winter/Spring  2015

  • Continued excavation of sand in Saugus and placement at Winthrop Beach
  • Creation of berm pathway in Saugus

Summer 2015

  • Drainage improvements and beach amenities at Pearl Avenue
  • Landscape and playground work at Crest Avenue

Fall 2015

  • Restoration of  Pearl Avenue Wall

More Information

DCR will continue to post information and updated schedules on this project web page.


Questions or concerns about the project should be directed to DCR Resident Engineer Steve Colometo, at the DCR trailer behind the DCR bathhouse on Winthrop Shore Drive, by visit or phone (617-539-4957) during regular business hours,  Monday through Friday from 7 a.m. – 3:00 p.m.   In case of an emergency, contact 911 or DCR’s 24/7 emergency hotline at the Massachusetts Emergency Management Agency at 508-820-1428.   


If you wish to be added to either a Winthrop Beach Nourish Project-specific or general information DCR listserv, please email mass.parks@state.ma.us, noting which listserv to which you wish to subscribe.   

Join us on Twitter @MassDCR - Visit http://mass.gov/dcr