CASE NUMBERCOMPANYLOCATIONDATE OF ORDERNOTES
DPU 13-86NSTAR Electric CompanyPetition for approval to construct two new 115kV underground transmission lines in the City of Boston, pursuant to G.L. c. 164, § 7211/4/14Order pdf format of Order
DPU 13-126/127NSTAR Electric CompanyPetition for exemption from Boston Zoning Code, pursuant to Section 6 of Chapter 665 of the Acts of 1956, and petition for approval to construct transmission lines in the City of Boston, pursuant to G.L. c. 164, §729/26/14Order pdf format of Order
file size 1MB
13-64NSTAR Electric CompanyPetition for exemption from zoning ordinance of the Town of Barnstable, pursuant to G.L. c. 40A, § 33/18/14Order
12-02New England Power Co./Mass. Electric Co.Petition of New England Power Company d/b/a National Grid for a determination pursuant to G.L. c. 164, § 72, and Petition of New England Power Company and Massachusetts Electric Company d/b/a National Grid for a Zoning Exemption pursuant to G.L. c. 30A, § 3.10/9/12Final Order
11-80NSTAR Electric CompanyPetition of NSTAR Electric Company for an Exemption from the Zoning By-laws of the Town of Plympton, pursuant to G.L. c. 40A, for proposed modifications to the Company's existing electric switching station of Brook Street in the Town of Plympton, Massachusetts.7/9/12Order
11-51NSTAR Electric Company and New England Power CompanyPetition of NSTAR Electric Company and New England Power Company d/b/a National Grid to G.L. c. 164, § 72 for Approval to Upgrade an Existing 115 kV Underground Transmission Line Located in the Cities of Boston and Everett, Massachusetts.2/27/12Order
DPU 11-26Tennessee Gas Pipeline CompanyPetition of Tennessee Gas Pipeline Company for certain Exemptions from the Zoning Bylaw of the Town of Southwick, Massachusetts, pursuant to G.L. c. 40A, § 3.1/6/12Order
DPU 09-136/09-137New England Power CompanyPetition of New England Power Company d/b/a National Grid pursuant to G.L. c. 164, § 72 to the Department of Public Utilities for a determination that the proposed construction of a new 115 kV overhead transmission line in the Towns of Millbury and Auburn, Massachusetts, are necessary and will serve the public convenience and be consistent with the public interest. Petition of New England Power Company d/b/a National Grid pursuant to G.L. c. 40A, § 3 to the Department of Public Utilities for certain exemptions from the Zoning Bylaws of the Towns of Millbury and Auburn, Massachusetts.10/13/11Order
DPU 10-77New England Power CompanyPetition for exemption from zoning ordinances, and determination of necessity relative to new 115 kV overhead transmission line in the towns of Easton and Mansfield, pursuant to G.L. c.164, §725/6/11Final Order
DPU 10-165/10-166/10-167Western Massachusetts Electric CompanyPetition of Western Massachusetts Electric Company for authority by the Department of Public Utilities, pursuant to G.L. c. 164, § 69R and § 72, to acquire by eminent domain under G.L. c. 79, easements necessary for the construction and use of transmission5/2/11Final Order
DPU 10-159Sheffield Water CompanyPetition for an exemption by the Department of Public Utilities from the zoning by-laws of the Town of Sheffield relative to the construction of a water tank, pursuant to G.L. c. 40A, § 35/2/11Final Order   
DPU 10-101CSX Transportation, Inc.Petition for authority to acquire property by eminent domain located at 255 and 320 Franklin Street, Worcester, pursuant to G.L. c.160, §833/1/11Notice of Dismissal
DPU 10-102CSX Transportation, Inc.Petition for authority to acquire property by eminent domain located at 255 and 310 Franklin Street, Worcester, pursuant to G.L. c.160, §832/18/11Notice of Withdrawal of Petition
DPU 10-103CSX Transportation, Inc.Petition for authority to acquire property by eminent domain located at 255 and 351 Franklin Street, Worcester, pursuant to G.L. c.160, §832/18/11Notice of Withdrawal of Petition
DPU 10-104CSX Transportation, Inc.Petition for authority to acquire property by eminent domain located at 255 and 567 Franklin Street, Worcester, pursuant to G.L. c.160, §832/10/11Notice of Dismissal of Petitions
DPU 10-105CSX Transportation, Inc.Petition for authority to acquire property by eminent domain located at 255 and 623 Franklin Street, Worcester, pursuant to G.L. c.160, §8312/8/10Notice of Dismissal
DPU 10-110Leroy & Co., Inc.Petition of Leroy & Co., Inc. to the Department of Public Utilities to Change Location of Taking, pursuant to G.L. c. 160, § 81, by CSX Transportation, Inc. at 567 Franiklin Street, Worcester, Massachusetts.2/10/11Notice of Dismissal of Petitions
DPU 10-127CSX Transportation, Inc.Petition for authority to acquire by eminent domain property at 0 and 57 Atlanta St, Worcester, pursuant to G.L. c. 160, § 8312/8/10Notice of Dismissal
DPU 10-128CSX Transportation, Inc.Petition for authority to acquire by eminent domain property at 15-17 Putnam Lane & Foch Ave, Worcester, pursuant to G.L. c. 160,  § 8312/8/10Notice of Dismissal
DPU 10-129CSX Transportation, Inc.Petition for authority to acquire by eminent domain property at 263 Grafton St, Worcester, pursuant to G.L. c. 160, § 8312/8/10Notice of Dismissal
DPU 10-130CSX Transportation, Inc.Petition for authority to acquire by eminent domain certain right-of-way interests in property abutting 169 and 177 Grafton St, Worcester, pursuant to G.L. c. 160, § 8312/8/10Notice of Dismissal
DTE/DPU06-60-CRussell Biomass LLCPetition for an exemption of a biomass generating facility from the Town of Russell Zoning By-laws5/26/10Order
DPU 09-27/09-28New England Power Company (NGRID)Petitions for exemptions from zoning ordinances of towns of Groveland, West Newbury, Merrimac and Amesbury; and determination of necessity to construct a 115 kV overhead transmission line, pursuant to G.L. c.40A, §3 and c.164, §72 in the towns of Groveland, West Newbury, Merrimac and Amesbury3/26/10Order
DPU 09-24/25Western Mass Electric Co. (WMECO)Petitions for exemptions from zoning ordinances of towns of Agawam and West Springfield, and approval to alter and operate as altered an existing transmission line, pursuant to G.L. to G.L. c.40A, '3 and c.164, §72 in the towns of Agawam and West Springfield3/19/10Final Order
DPU 06-60-B

Russell Biomass LLC

Order on Compliance Filing

12/4/09Final Order
DPU 08-103NE Power Company d/b/a National GridPetition for determination regarding the proposed relocation of a portion of two (2) existing 115kV overhead transmission lines in the City of Lynn, pursuant to G.L. c.164, §7210/30/09Final Order
DPU 08-1NSTAR Electric CompanyPetition seeking approval to construct and operate transmission lines, and exemptions from the zoning code of the City of Waltham, pursuant to G.L. c.164, §72 and G.L. c.40A, §39/25/09Final Order
DTE 06-60Russell Biomass LLCPetition for an exemption of a biomass generating facility from the Town of Russell Zoning By-laws8/22/08Order
DPU 07-80Mass Electric Co., New England Power Co and PPM Energy, IncJoint Petition for determination that approx. 6.1 mile 34.5kV tie line in the Towns of Florida and Monroe7/14/08Final Order
DPU 07-60/07-61

NSTAR Electric Company

Petition of NSTAR Electric Company pursuant to G.L. c. 164, § 72 for approval to construct and operate new transmission lines in the Towns of Carver, Middleborough, Rochester and Wareham, and Petition pursuant to G.L. c. 40A, § 3 for exemption from the Zoning By-Laws of Carver and Wareham to expand facilities at two electric substations.4/2/08Order
DTE 07-9/DTE 07-10NSTAR Electric CompanyPetition for zoning exemption pursuant to G.L. c.40A, §3 to construct and operate a proposed expanded electric switching station; and a Petition pursuant to G.L. c.164, §72 to construct a electric transmission line, in the Town of Plympton11/26/07Final Order
DPU 06-11Princeton Municipal Light Department

Petition for an exemption of wind electric generating facilities from the Town of Princeton Zoning By-Laws

9/24/07Order
DPU 07-62Algonquin Gas Transmission, LLC 

Petition, pursuant to G.L. c.164, § 72A and § 75B and 75D, for authorization enter upon land owned by various persons, entities or corporations to make surveys associated with an application to FERC for construction of natural gas pipelines and facilities

9/18/07Authority to enter upon land, survey

DTE 06-37

NSTAR Electric Company

Towns of Uxbridge and Northbridge

1/12/07Final Order
DTE 05-1Commonwealth Electric Company d/b/a NSTAR ElectricTown of Barnstable7/12/05Final Order
DTE 04-81MASSACHUSETTS ELECTRIC COMPANYPetition of Massachusetts Electric Company for approval by the Department of Telecommunications and Energy for an exemption from the operation of the Zoning Code of the City of Haverhill, Massachusetts with respect to the construction of proposed electric5/26/05Order
DTE 04-71BOSTON EDISON COMPANY D/B/A NSTARPetition of Boston Edison Company d/b/a NStar Electric for approval by the Department of Telecommunications and Energy, to construct and operate a Transmission Line, pursuant to G.L. c. 164, § 72, in the Towns of Framingham, Natick and Sherborn, Massachusetts3/31/05Order
DTE 04-66NEW ENGLAND POWER COMPANYPetition of New England Power Company for exemption of an electric substation additions from the zoning code of the City of Haverhill, Massachusetts.3/3/05Order
DTE 04-04New England PowerPetition of New England Power Company for Zoning Exemption from the Town of West Boylston, Massachusetts, in the Proposed Expansion of its Wachusett No. 47 Substation.12/21/04Final Order
DTE 04-10Nantucket Electric CompanyPetition of Nantucket Electric Company for a determination by the Department of Telecommunications and Energy, under the provisions of G.L. c. 164, § 72, that a proposed 33-mile underground and submarine 46 kV distribution line from Barnstable to Nantucket is necessary and will serve the public convenience and is consistent with the public interest.12/21/04Final Order
DTE 04-26Mill River Pipeline, L.L.C.City of Fall River and the Town of Somerset, Massachusetts4/26/04Order
DTE 03-130Massachusetts ElectricGroveland and Georgetown, Massachusetts3/26/04Order
DTE 03-83USGen New England, IncSalem; zoning exemption6/22/04Final Order
DTE 03-7Commonwealth Electric CompanyBarnstable4/29/03Zoning Exemption Order
DTE 01-57Tennessee Gas Pipeline CompanyAgawam; zoning exemption4/17/02Final Decision
DTE 01-77Massachusetts Electric CompanyWestford; zoning exemption4/23/02Final Decision
D.T.E. 01-48Maritimes and NortheastAndover, Middletown, Danvers, Haverhill, Peabody8/1/01Authority to enter upon land, survey
D.T.E. 01-48AMaritimes and NortheastBoxford, North Andover, and Middleton11/13/01Authority to enter upon land, survey
D.T.E. 01-48BMaritimes and NortheastHaverhill2/6/02Authority to enter upon land, survey
D.T.E. 00-34Maritimes and NortheastMethuen, Boxford, North Andover, Middletown, Danvers, Haverhill, Peabody, Salem5/11/00Authority to enter upon land, survey
D.T.E. 00-98TennesseeAgawam, West Springfield1/11/01Authority to enter upon land, survey
D.T.E. 00-24Boston GasDanvers2/22/01Zoning exemption
D.T.E. 99-57Boston EdisonMendon and Blackstone9/9/99Approval of transmission line and eminent domain
D.T.E. 99-50TennesseeMendon4/27/00Zoning exemption
D.T.E 99-35WMECOAgawam9/15/99Zoning exemption
D.T.E. 98-105Grafton and Upton RailroadGrafton11/22/99Zoning exemption
D.T.E. 98-102Sprint SpectrumSturbridge4/7/99Zoning exemption
D.T.E. 98-33TennesseeAgawam12/10/98Zoning exemption
D.P.U 96-104Berkshire Power DevelopmentAgawam10/22/97Zoning exemption
D.P.U. 96-45MMWECLudlow, Wilbraham, Hampden, Monson, Palmer7/18/96Authority to enter upon land, survey
D.P.U.
96-45A
MMWECLudlow, Wilbraham, Hampden, Monson, Palmer8/2/96Authority to enter upon land, survey
D.P.U.
96-45B
MMWECLudlow, Wilbraham, Hampden, Monson, Palmer8/15/96Authority to enter upon land, survey
D.P.U.
96-45C
MMWECLudlow, Wilbraham, Hampden, Monson, Palmer9/27/96Authority to enter upon land, survey
D.P.U.
96-45D
MMWECLudlow, Wilbraham, Hampden, Monson, Palmer11/18/96Authority to enter upon land, survey
D.P.U.
96-45E
MMWECLudlow, Wilbraham, Hampden, Monson, Palmer4/27/97Authority to enter upon land, survey
D.P.U. 95-120Massachusetts American Water Co.Hingham8/6/96Eminent domain
D.P.U./D.T.E. 95-80Nextel CommunicationsMarlborough3/2/99Zoning exemption
D.P.U. 95-59NextelSterling2/9/96Zoning exemption
D.P.U.
95-59A
NextelSterling7/19/96Zoning exemption
D.P.U./D.T.E. 95-59B/95-80/
95-112/96/13
Nextel et al.Investigation into Public Service Corporation status of commercial mobile radio service1/8/98
 



 


This information is provided by the Department of Public Utilities