Roadway improvements including bicycle and pedestrian upgrades on Route 203 between West Selden Street and Gallivan Boulevard in the Mattapan section of the City of Boston.

Table of Contents

Project Schedule

Fall 2019:  Complete all utility underground.  Complete majority of sidewalk reconstruction.  New street lighting equipment will be installed.

Winter 2019/2020:  Installation of new traffic signal equipment and mast arms.

Spring 2020: Landscaping, new signage, mill and pave.  Energize new street lighting and traffic signals.

Summer 2020: Punch list items and project close out.

Upcoming Improvements

  • New concrete sidewalks/ramps - approximately 95% complete
  • New street lighting & traffic signal work - 95% complete
  • Interconnected Traffic Signals Norfolk to Gallivan
  • Replace Pedestrian Signals & Pushbuttons Norfolk & Evans
  • New Street Lighting West Selden to Gallivan
  • New Pavement Surface, Sidewalks, and Driveways West Selden to Gallivan
  • Introduce Bicycle Lanes West Selden to Gallivan
  • Replace Traffic Signal at West Selden
  • New Traffic Signal at Gallivan

Construction

  • Work to begin June 2019
  • First operations will be signage and other initial work
  • Work Hours: 7AM to 4PM
  • Some work must be done at night but for short periods
  • Utility companies may be working at night
  • Completion date June 2020

Getting Around

Lane Closures

  • Cannot close a lane between: 6AM 10AM and 3PM 7PM
  • One travel lane in each direction will be open at all times
  • Close coordination with Boston Fire Department

Pedestrians

  • Detours during sidewalk reconstruction
  • Detours will have clear signage and guide pedestrians to the nearest crosswalk

MBTA

  • Bus stops may be temporarily relocated during sidewalk work
  • Our goal is to have all temporary stops located within 100 feet of the existing stop