About the Route 44 over Route 24 Bridge Replacement Project

Learn about the project to replace the existing bridge carrying US Route 44 over State Route 24 in Raynham, Massachusetts.

Table of Contents

Project Details

The primary goal of the Route 44 over Route 24 Bridge Replacement Project is to replace the existing bridge structure, which is structurally deficient and functionally obsolete. The project will use a bridge lateral slide technique during an overnight shutdown and detour of both Route 24 and Route 44, allowing traffic to be temporarily shifted south and making it possible to construct the bridge in phases. This will reduce traffic impacts and detours of Route 24 traffic and minimize the amount of traffic shifts on Route 44 when compared to a typical construction approach.

For this project, MassDOT has utilized Design-Build Project delivery where one entity is responsible for both the design and construction. This alternative contracting method not only helps reduce the time needed to carry out the project, but also promotes collaboration between the engineers, contractor, and MassDOT staff.

Other project goals include incorporating functionality and safety improvements into the roadway and highway interchange system between South Street West and Orchard Street on Route 44. The project also includes:

  • Improving pedestrian, bicycle, and ADA accommodations along Route 44
  • Reconstructing on and off ramps between Route 44 and Route 24
  • Improving the roadway drainage system
  • Installing interim and final traffic signals
  • Relocating utilities
  • Addressing traffic weaving issues on Route 24 southbound
  • Raising vertical clearance of the bridge
  • Widening the bridge
  • Restoring landscaping

Anticipated Project and Work Schedule

Work Schedule

 Monday through Friday from 6:00 AM to 4:00 PM and 8:00 PM to 5:00 AM the following morning.

Project Schedule

  • July 2018 - October 2018: Median and ramp construction
  • October 2018 - June 2019: Construction of southern half of bridge
  • June 2019 - September 2019: Construction of middle portion of bridge
  • September 2019: Bridge slide (southern portion)
  • September 2019 - March 2021: Utility relocations
  • March 2021 - July 2021: Construction of remaining northern portion of bridge
  • July 2021 - September 2021: Median restoration and final paving
  • October 2021: Final completion

 

Project Team

MassDOT – Owner

SPS New England – Design-Build Entity

VHB – Lead Designer

Regina Villa Associates, Inc. – Public Outreach