Traffic and Construction Updates - Route 28 in Reading

Information on traffic and construction during resurfacing and road diet pilot

Table of Contents

North Section (North Main Street)

Work completed in Fall 2019

  • Installed intermediate pavement layer

Work completed in 2020

  • Installed and revised pilot pavement markings
  • Construction of curb ramps, sidewalks, guard rails, and driveways

Work scheduled for Spring and Summer 2021

  • Install final pavement layer and markings

South Section (South Main Street)

Work completed in 2020

  • Installed intermediate pavement layer 
  • Installed and revised pilot pavement markings
  • Construction of curb ramps, sidewalks, guard rails and driveways
  • National grid completes emergency gas repairs and upgrades

Work scheduled for Fall 2021

  • Install final pavement layer and markings

National Grid Utility Upgrades

  • In April 2020, National Grid began necessary upgrades to utility infrastructure on Main Street in Reading. The utility upgrades were completed in October 2020.
  • While the utility upgrades are not part of MassDOT's Route 28 Resurfacing and Road Diet Pilot project, National Grid and MassDOT are working closely to coordinate the two projects.
  • In Spring 2021, roadway surfaces that were impacted by the utility work on Main Street will undergo trench restoration to provide a smoother roadway surface before the final pavement surface is installed.