The abatement phase of Lindemann Gym Floor Replacement Project will start on Thursday, May 17, 2018 and run through Monday, May 21, 2018. The Gym will be closed during the abatement and demolition work; only the Work-out / Exercise section will be reopened thereafter. The abatement work schedule will be executed as follows;
Date |
Location |
Construction Activity |
Thursday 05/17/18 |
The entire Gym Floor Areas |
Abatement Mobilization & Prep Work |
Friday 05/18/18 |
Gym Entrance Lobby Area |
VAT Floor Tile Abatement and Visual Clearance / Floor Carpet Removal |
Saturday 05/19/18 |
Gym Perimeter Areas and Locker RM Corridor |
VAT Floor Tile Abatement and Visual Clearance |
Monday 05/21/18 |
The entire Gym Floor Areas |
Construction Tear Down and Demobilization |
The work time is from 7:00 AM to 4:00 PM. The abatement contractor will ensure adequate safety by installing poly containment barriers at the abatement areas and set up HEPA filtered ventilation units for negative air exhaustion and would prevent fugitive emissions of visible dust. We will coordinate with DMH Facilities, Safety & Security and program directors in order to avoid any major impact or disruption to other business activities in the building.
We apologize for any inconvenience this may cause and appreciate your understanding and cooperation in getting this project done in a reasonable time frame. If you have any questions or concerns, please call the Facility Manager at 617-455-1270 or after business hours; call the Control Center at 617-727-1000.