Making Progress Cleaning Up Contaminated Properties

The Massachusetts Contingency Plan was significantly revised effective October 1, 1993 when a new, privatized approach was adopted. Since then, DEP has worked with private-sector Licensed Site Professionals (LSPs) to assess and cleanup sites. This page asks and answers questions about the progress of cleanups since 1993.

This information is current through Fiscal Year 2025.

Table of Contents

Notifications - Summary

58,440  Releases Reported since 1984
  • How many releases have been reported to DEP?
    Since 1984, more than 58,000 releases have been reported to the Department.
     
  • What accounts for the most notifications: sudden releases (spills) or historic contamination?
    Two-hour notifications, primarily related to new spills, account for 57 percent of all the notifications received since 2011. The balance of notifications is split between: 120-Day notifications, generally associated with finding historic contamination at concentrations above Reportable Concentrations; and 72-Hour notifications, which include (among other conditions) leaking tanks, groundwater contamination near a public well or near/at a private well, and actual/potential impacts to indoor air.
     
  • Are the numbers of spills increasing each year?
    No. There has been an overall decline of all three types of notifications (2-Hour, 72-Hour and 120-Day) over time.  This trend is consistent with better environmental management practices, upgrades in underground storage tanks, and a diminishing universe of undiscovered "historic" contamination. The notable increase in 72-Hour notifications in 1999 is attributable to the discovery of contamination related to leaking underground storage tanks driven by the federal deadline for the upgrade or replacement of underground storage tanks. 
Releases by notification category for FY25

Cleanup & Closures - Summary

45,332  Sites Closed Since 1993
  • How many sites have been cleaned up since 1993?
    45,332 sites, averaging over 1400 per year. 
     
  • How many sites have been cleaned for unrestricted use?
    A Permanent Solution with No Conditions has been achieved at 40,401 sites (or almost 90%), indicating that the site is suitable for unrestricted use. (This includes sites that have achieved Class A-1, A-2, and B-1 Response Action Outcomes – the closure categories that were in place prior to the 2014 regulatory changes.)
     
  • How many sites have achieved temporary solutions?
    A Temporary Solution has been achieved at 956 (2%) of the sites cleaned up to date. (Temporary Solutions were referred to Class C RAOs prior to Spring 2014.)
     
  • At how many of the sites with a Permanent Solution was a deed notice or restriction (i.e., an Activity and Use Limitation) used as part of the remedy?
    Between 1994 and 2025, 7% of Permanent Solutions included an Activity and Use Limitation (AUL) as part of the final remedy. 
Cleanups and Site Closures Through FY25
Trends in AULs for FY25

Note:  FY2021: the number of sites closed with AULs did not increase significantly over past years, so the observed percentage increase may be due more to the drop in 2-hour notifications during the pandemic.  2-Hour notifications tend to be closed without AULs.  Time will tell if this is a trend.

  • How long does the cleanup process take?
    Over 90% of the releases from FY95 to FY19 have achieved regulatory closures in less than six years from the time of notification. Over the past 15 years, this measure appears to have stabilized at approximately 93% (+/-).  For the purpose of the chart below sites with regulatory closure include those with the compliance status of: Permanent Solution with No Conditions, Permanent Solution with Conditions, Adequately Regulated, Downgradient Property Status, RTN Closed, Memorandum of Understanding (DEPMOU), Not a Disposal Site (DEPNDS), DEP No Further Action (DEPNFA), LSP No Further Action (LSPNFA), Pending Not a Disposal Site (PENNDS), Pending No Further Action (PENNFA), Special Project (SPECPR), Utility-related Abatement Measure (URAM), Waiver Completion Statement (WCSPRM).
     

The chart below shows the length of time to achieve a Permanent or Temporary Solution from the time of notification by notification type (2-Hour, 72-Hour or 120-Day). The time required to achieve a Permanent or Temporary Solution is less than 6 years in the vast majority of cases and for all notification types (2 Hour - 97%, 72 Hour - 91%, 120 Day - 92%).  Note that pre-FY1994 sites (Notification Category = "None") required significantly more time to achieve closure.

Time  to achieve a Permanent or Temporary Solution FY25

The chart below shows the current status of notifications made in FY2019.  The chart shows that for the majority of sites for which the notification was made either a Permanent Solution has been achieved or a Permanent/Temporary Solution is not required within 6 years.  (The most common reasons why a Permanent or Temporary Solution is not required is because the notification condition has been “linked” (i.e., response actions consolidated) under another notification and release tracking number.  Other reason include the site is considered Adequately Regulated, Downgradient Property Status has been achieved or a Utility-related Abatement Measure is being conducted.)

The current status of notifications made in FY2019

Immediate Response Actions

Immediate Response Actions (IRAs) are required to address any condition that triggers a 2-Hour or 72-Hour notification to the Department.  IRAs are expedited response actions that include at a minimum assessment, and where appropriate, actions to contain, isolate, or remove contamination from the environment that is the result of a release or address a threat of release.  IRAs require approval by the Department.  The chart below shows IRA approvals (both oral and written) by the Department by Fiscal Year (FY).

IRA approvals for FY25

Audits

61,009  Number of Audits conducted by MassDEP since FY2000

Since FY2000 MassDEP has conducted over 61,000 audits of response action submittals to evaluate and ensure compliance of those submittals and the associated response actions with the Massachusetts Contingency Plan.  MassDEP conducts three different types of audits, which are referred to as Level 1 (Technical Screening Audit), Level 2 (Audit Inspection), and Level 3 (Comprehensive Audit).  (Link to Audits Page) The majority of all audits conducted by MassDEP over time (86%) have been Level 1 Audits.  The chart below shows the number of audits completed by fiscal year and the type of audit.

Audits completed by FY25

Notifications - Year-by-Year Data

Fiscal Year2-Hour72-Hour120-Day"None"Total
19850002121
1986000194194
198700012211221
1988000399399
198900012951295
199000011621162
1991000623623
1992000505505
1993000551551
199410527112269452934
1995107668146902226
199698653566102182
1997103354261402189
199896763066302260
199997489473002598
2000100346573402202
2001113741366502215
200299243857302003
2003102133657701934
2004102830652101855
200597533552901839
200693138651501832
200788328755701727
200867829349501466
200974525143601432
201071723634801301
201173421837801330
201268725240701347
201366518338501233
201461922438901232
201566020039101251
201667019937401243
201769321341001316
201881320235801373
201980613532101262
202070614137601223
202161712233101070
202271314735801218
202365613830401098
202468910222401015
202570112923301063
Total-to-Date:266471036514608682058440

Cleanup & Closures - Year-by-Year Data

Fiscal YearaPSNCbPSCbTMPSbGrand Total
1994609121622
199519038281993
1996161910891736
19971956177122145
19981754202231979
19991778138211937
20001633129281820
20011713119221854
2002163496211751
20031590120241734
20041637115291781
2005155593291677
20061605114321751
2007149790341621
20081284102241410
2009131987371443
20101199106481353
20111056116441216
2012121685321333
2013104279331154
2014100399311133
2015913147321092
2016925164301119
2017966195301191
20181047167431257
2019965146421153
2020935160331128
202179416040994
202282613436996
2023806156431005
2024822148371007
202577012948947
Grand Total40401397595645332

For a complete explanation of the terms and acronyms used here, see the document, "Understanding the Waste Site/Release Look Up Search Results" below.

a Prior to June 20, 2014, the Massachusetts Contingency Plan (MCP) used different Response Action Outcome (RAO) classes to identify Permanent and Temporary Solutions. After the June 2014 MCP amendments, RAO classes were recategorized into types of Permanent or Temporary Solutions in accordance with the transition provisions at 310 CMR 40.1055 (see below).

310 CMR 40.1055 Transition Provisions

  • (1) As of June 20, 2014, all Class A-1, A-2 and B-1 Response Action Outcomes submitted to the Department prior to June 20, 2014 shall be Permanent Solutions with No Conditions.
  • (2) As of June 20, 2014, all Class A-3, A-4, B-2 and B-3 Response Action Outcomes submitted to the Department prior to June 20, 2014 shall be Permanent Solutions with Conditions.
  • (3) As of June 20, 2014, all Class C-1 Response Action Outcomes submitted to the Department prior to June 20, 2014 shall be Temporary Solutions as described in 310 CMR 40.1050(1)(e)1.
  • (4) As of June 20, 2014, all Class C-2 Response Action Outcomes submitted to the Department prior to June 20, 2014 shall be Temporary Solution as described in 310 CMR 40.1050(1)(e)2.

b

  • PSNC - Permanent Solution with No Conditions
  • PSC - Permanent Solution with Conditions
  • TMPS - Temporary Solution

EEA Data Portal

The Data Portal provides access to search and interact with regulatory data, including MassDEP data pertaining to Permits, Facilities, Inspections, and Enforcements.

Help Us Improve Mass.gov  with your feedback

Please do not include personal or contact information.
Feedback