41,377
Sites Closed Since 1993
- How many sites have been cleaned up since 1993?
41,377 sites, averaging over 1400 per year.
- How many sites have been cleaned for unrestricted use?
A Permanent Solution with No Conditions has been achieved at 36,964 sites (or more than 89%), indicating that the site is suitable for unrestricted use. (This includes sites that have achieved Class A-1, A-2, and B-1 Response Action Outcomes – the closure categories that were in place prior to the 2014 regulatory changes.)
- How many sites have achieved temporary solutions?
A Temporary Solution has been achieved at 927 (2%) of the sites cleaned up to date. (Temporary Solutions were referred to Class C RAOs prior to Spring 2014.)
- At how many of the sites with a Permanent Solution was a deed notice or restriction (i.e., an Activity and Use Limitation) used as part of the remedy?
Between 1994 and 2022, 8% of Permanent Solutions included an Activity and Use Limitation (AUL) as part of the final remedy.


Note: FY2021: the number of sites closed with AULs did not increase significantly over past years, so the observed percentage increase may be due more to the drop in 2-hour notifications during the pandemic. 2-Hour notifications tend to be closed without AULs. Time will tell if this is a trend.
- How long does the cleanup process take?
Over 89% of the releases from FY95 to FY15 have achieved regulatory closures in less than six years from the time of notification. Over the past 15 years, this measure appears to have stabilized at approximately 92% (+/-). For the purpose of the chart below sites with regulatory closure include those with the compliance status of: Permanent Solution with No Conditions, Permanent Solution with Conditions, Adequately Regulated, Downgradient Property Status, RTN Closed, Memorandum of Understanding (DEPMOU), Not a Disposal Site (DEPNDS), DEP No Further Action (DEPNFA), LSP No Further Action (LSPNFA), Pending Not a Disposal Site (PENNDS), Pending No Further Action (PENNFA), Special Project (SPECPR), Utility-related Abatement Measure (URAM), Waiver Completion Statement (WCSPRM).
The chart below shows the length of time to achieve a Permanent or Temporary Solution from the time of notification by notification type (2-Hour, 72-Hour or 120-Day). The time required to achieve a Permanent or Temporary Solution is less than 6 years in the vast majority of cases and for all notification types (2 Hour - 97%, 72 Hour - 87%, 120 Day - 89%). Note that pre-FY1994 sites (Notification Category = "None") required significantly more time to achieve closure.

The chart below shows the current status of notifications made in FY2016. The chart shows that for the majority of sites for which the notification was made either a Permanent Solution has been achieved or a Permanent/Temporary Solution is not required within 6 years. (The most common reasons why a Permanent or Temporary Solution is not required is because the notification condition has been “linked” (i.e., response actions consolidated) under another notification and release tracking number. Other reason include the site is considered Adequately Regulated, Downgradient Property Status has been achieved or a Utility-related Abatement Measure is being conducted.)