What you need to know
Please be informed that the next phase of ADA, Door Hardware and Security Improvement project will start at Lindemann Building on Thursday, March 22nd. The work schedule will be executed as follows;
Date |
Location |
Door # |
Construction Activity |
Day 3 To Day 5 |
Hurley: 5th Floor, Part 2 – Elevator lobby, corridor egress door. |
Door #23 |
Replace existing double doors with a 36” wide door and side lite. Card reader on lobby side. |
Day 5 To Day 6 |
Hurley: 6th Floor, Corridor door at Minihan Hall entrance. |
Door #26 |
Replace existing double doors with a 48” wide door –match exiting frame. Electro-magnetic holder connected to fire alarm system (Release button for egress. |
Day 7 To Day 8 |
Lindemann: Ground Floor, Cafeteria Exit Door to Elevator Lobby – South side |
Door #30 |
Replace existing double doors with a 42” wide door. Install panic bar with key lock on lobby side. |
Day 8 To Day 9 |
Lindemann: Ground Floor, Cafeteria Exit Door to Elevator Lobby – North side |
Door #31 |
Replace existing double doors with a 42” wide door. Install panic bar with key lock on lobby side. |
The work time is from 6:30 AM to 3:30 PM. The project is expected to last for about three months. The revised project base schedule is available upon request. We will coordinate with the respective user agencies and programs in the building to avoid any major impact or disruption to the normal business activities.
We apologize for any inconvenience this may cause and appreciate your understanding and cooperation in getting this project done in a reasonable time frame. If you have any questions or concerns, please call the Facility Manager at 617-455-1270 or after business hours; call the Control Center at 617-727-1000.