Overview
Contractor: Constellation NewEnergy, Inc.
Cost: $13,400.000
Annual Cost savings $1,100,000
Annual savings:
- Oil #6 (gallons) – 643,722
- Natural Gas (therms) – (413,293)
- Water (gallons) – 7,344,000
- CO2 (metric tons) – 3,800
Project goals:
- Switch from oil to gas and reduce greenhouse gas emissions
- Replace aging central boilers
- Improve comfort of main inmate housing
Project features
- New natural gas boiler plant
- New natural gas boilers for small buildings
- New windows
- New gas dryers
- Insulation