Brighton District Court - Accessibility and Deferred Maintenance Improvements

Project included miscellaneous repairs to address deferred maintenance and accessibility improvements.

Project Details

Brighton District Court Envelop Repairs

Project Type:  Design, Bid, Build 
Study Designer:  Kessler McGuiness & Associates
Project Designer:  Simpson Gumpertz & Heger
Contractor: TRAC Builders, Inc.
Gross Square Feet:  23,675
Estimated Project Cost:  $11.5 million

Est. Substantial Completion Date: Fall 2020

Project Features

  • Reconstruction of front entry steps, ramps and landing
  • Replacement of low-slope membrane roofing and slate roofs
  • Replacement of roof-top mechanical equipment
  • Replacement of existing fire alarm system
  • Accessibility improvements