Organization: | Office of the State Auditor |
---|---|
Date published: | July 19, 2018 |
Executive Summary
In accordance with Section 12 of Chapter 11 of the Massachusetts General Laws, the Office of the State Auditor has conducted a performance audit of the Massachusetts Port Authority’s (Massport’s) administration of design and construction contracts for the Logan Airport Terminal E Renovation and Enhancement Project for the period July 1, 2014 through June 30, 2017.
In this performance audit, we examined whether Massport’s administration of its design service contract with AECOM USA of Massachusetts and its construction service contract with Suffolk Construction Company, Inc. was consistent with applicable laws, regulations, contractual terms and conditions, and other guidance.
Our audit revealed no significant instances of noncompliance that must be reported under generally accepted government auditing standards.
A PDF copy of the audit of the Massachusetts Port Authority is available here.
Abbreviations
CP&EA |
Department of Capital Programs & Environmental Affairs |
DCAMM |
Division of Capital Asset Management and Maintenance |
Massport |
Massachusetts Port Authority |
OIG |
Office of the Inspector General |
SCC |
Suffolk Construction Company, Inc. |
Table of Contents
Contact
Phone
Online
Fax
Address
Room 230
Boston, MA 02133