WS 33: Distribution Modifications for Systems that serve 3,300 people or fewer

Approval for altering a distribution system

MassDEP Drinking Water Program

The Details of WS 33: Distribution Modifications for Systems that serve 3,300 people or fewer

What you need for WS 33: Distribution Modifications for Systems that serve 3,300 people or fewer

This approval serves to protect the public's health and welfare by insuring that minimum drinking water requirements are met in the modification of a drinking water distribution system, such as storage tanks, distribution pump stations, and transmission main installation. Legislative authority is stated in MGL Chapter 111, section 160A. Regulatory authority is stated in 310 CMR 22.04 of the Drinking Water Regulations.

Public water suppliers or their representatives must apply if they want approval for modification of their distribution system.

If the water supplier or their representative apply for this approval it may be necessary to apply for other water treatment approvals WS 23 or WS 24.

Note: Approvals of this type may require MEPA review. Please carefully examine 301 CMR 11.00, the MEPA Regulations, to determine if your project exceeds the MEPA review thresholds, or for more information contact the MEPA Unit of the Executive Office of Environmental Affairs (251 Causeway Street, Suite 900, Boston MA 02114 (617) 626-1020). MassDEP cannot begin technical review of the application until the MEPA process has been completed, unless otherwise agreed to in writing. Copies of MEPA filings (with reference to any applicable Transmittal numbers) should be sent to the appropriate program offices in Boston and the MEPA Coordinator in the appropriate Regional Office.

Note: These additional requirements are intended to serve as a guide to the applicant. It does not necessarily include all additional requirements.

How to apply WS 33: Distribution Modifications for Systems that serve 3,300 people or fewer

See details below.

Next steps for WS 33: Distribution Modifications for Systems that serve 3,300 people or fewer

  1. Review the instructions

    Guidance on how to prepare your application, including a completeness checklist.

  2. Complete the Application Form

    You may fill out and save the Microsoft Word form on your computer.  The PDF version has to be printed out and completed by hand.

  3. Obtain a Transmittal Form and Number

    A unique Transmittal Number is needed for each application you submit to MassDEP.

  4. Lookup the Permit Application Fee

  5. Mail Your Application and Fee Payment

    Submit your application fee payment and a copy of your Transmittal Form to:

    Department of Environmental Protection
    P.O. Box 4062
    Boston, MA 02211

    Submit your completed, signed application and your original Transmittal Form to the appropriate MassDEP Regional Office (see listing below).

Contact for WS 33: Distribution Modifications for Systems that serve 3,300 people or fewer

Address
MassDEP Boston
1 Winter Street, Boston, MA 02108

Feedback

Did you find what you were looking for on this webpage? * required
We use your feedback to help us improve this site but we are not able to respond directly. Please do not include personal or contact information. If you need a response, please locate the contact information elsewhere on this page or in the footer.
We use your feedback to help us improve this site but we are not able to respond directly. Please do not include personal or contact information. If you need a response, please locate the contact information elsewhere on this page or in the footer.

If you need to report child abuse, any other kind of abuse, or need urgent assistance, please click here.

Feedback