About the I-295 ramp & I-95 southbound over Ten Mile River project

This project will improve the ramp between I-295 northbound and I-95 southbound in Attleboro, MA by removing the old ramp and constructing a new ramp.

Table of Contents

Overview

The goal of this project is to improve the safety and efficiency of the existing ramp between I-295 northbound and I-95 southbound.

The scope of this project entails:

  • The realignment of the ramp to improve traffic flow onto I-95 southbound.
  • The existing ramp bridge superstructure will be removed as part of the ramp closure.
  • The bridge on I-95 over Ten Mile River will be widened to accommodate the lengthening of the existing acceleration lane.
  • Construction of new roadway merge and diverge areas, approach guardrails, guardrails, and drainage improvements are also part of this project.
  • The bridge rail on the east side (far left travel lane) of the I-95 bridge over Ten Mile River will also be replaced.

MassDOT will develop a construction plan that lessens temporary construction impacts on the community and traveling public.

Construction and traffic management

Major construction for this project (started in 2024) is complete and the new I-295 to I-95 South ramp is now open. Currently the project does not anticipate any further major traffic disruptions related to this project.

Construction photos

View of deck beam and crew members at night.

Crews install bridge deck beam on I-95 southbound (June 2024).

A view of the installation with crew in the background.

Bridge approach slab and barrier installation (August 2024).

A crew member monitors the concrete pour.

Crew pours concrete for bridge deck beam (July 2024).

Construction equipment at the ramp site.

Site preparation for new I-95 southbound ramp site (August 2024).

Paving of new I-95 ramp (October 2024).

Paving of new I-95 ramp (October 2024).

Surfacing of roadway at new I-95 ramp (May 2025).

Surfacing of roadway at new I-95 ramp (May 2025). 

Roadway reflector installation at new I-95 ramp (June 2025).

Roadway reflector installation at new I-95 ramp (June 2025).

Construction impact mitigation included:

  • Traffic diversions
  • Signed detours for ramp closures
  • Dust and pollutant containment
  • Keeping abutters and users informed through public outreach
  • Night and weekend work to minimize traffic impacts

Staying informed

Continue to visit the project website for more information on the project, impacts, and how to get involved and stay informed.

If your neighborhood organization, advocacy group, or other community organization would like to request a briefing, please send an email to: i95rampattleboro@dot.state.ma.us.

Contact

Help Us Improve Mass.gov  with your feedback

Please do not include personal or contact information.
Feedback