Traffic and construction updates - Maffa Way/Mystic Ave. Bridge project

Project status and construction and traffic management updates

Table of Contents

Construction activities are in progress. Weather and unexpected circumstances make all construction activities subject to change without notice, but we will do our best to keep you updated.

Phase II Traffic and Construction (January 2025 – Winter 2025/2026)

Phase II of the project began in January 2025 and includes the replacement of the south side of the Maffa Way Bridge and the north side of the Mystic Avenue Bridge. MassDOT implemented traffic shifts on both the Maffa Way Bridge and the Mystic Avenue Bridge in January 2025 to accommodate Phase II construction.

On Mystic Avenue, two lanes of traffic are shifted to the newly constructed south side of the bridge. On Maffa Way, two lanes of traffic are shifted onto the newly constructed north side of the bridge. One lane from Broadway in Somerville and one lane from the I-93 ramp will be maintained. Pedestrian access will be maintained across the bridge.

Maffa Way cross-section showing widths of travel lanes, shoulder and sidewalk.
Construction conditions on Maffa Way Bridge during Phase II.

On the Maffa Way Bridge, vehicular travel is reduced to two lanes and the south side of the bridge is closed for construction. 

Mystic Avenue cross-section showing travel lane, shoulder and sidewalk widths.
Construction conditions on Mystic Avenue Bridge during Phase II.

On the Mystic Avenue Bridge, vehicular travel is reduced to two lanes and the north side of the bridge is closed for construction.

Vehicular and Pedestrian Detours for Phase II

In order to establish the work zones for Phase II, the following local detours were implemented in January 2025 and anticipated to remain in place through January 2026. Appropriate signage and messaging will be in place to guide drivers through the work areas. 

View the detour maps in EnglishSpanishPortuguese, and 简体中文.

Brighton Street at Broadway Closure Detour (see detour map):

  • Vehicles traveling from Caldwell Street to Maffa Way should turn right on Brighton Street, right on Perkins Street, left on Parker Street, and left on Cambridge Street.
  • Vehicles traveling from Broadway to Brighton Street should turn onto Mount Pleasant Street, then turn left onto Perkins Street.
  • Pedestrians will be directed to use Caldwell Street, Perkins Street, and Mount Pleasant Street (see pedestrian detour map).

Sherman Street at Mystic Avenue Closure Detour (see detour map):

  • Vehicles traveling from Mystic Ave to Sherman St. will be directed to turn right on Dorrance St. and left on Arlington Ave.
  • Vehicles traveling from Sherman St. to Mystic Ave will be directed to head north on Sherman St., turn right on Arlington Ave, and turn right on Dorrance St.

What you can expect

Abutters, motorists, cyclists, and walking pedestrians should expect to see more construction activities in the area and should consider adding additional time for their commutes.

During these activities, crews will be working during standard construction hours, 7:00 AM – 3:00 PM Monday – Friday, except during certain periods coinciding with the temporary shutdown of MBTA train and rail services in the area.

Contact

Phone

The project telephone hotline will be staffed Monday – Friday between the hours of 7:00 AM and 4:00 PM. Calls received outside of these hours will be returned during the next business day.