Advisories
Advisories will be posted as they become available.
Construction look-ahead October 25 – November 7, 2026
What is happening?
The contractor is continuing with roadway and bridge construction activities and bridge demolition operations. Demolition operations are taking place above active roadways. This work is scheduled during overnight hours when traffic volumes are lower and easier to divert, and as a safety measure for the public and the contractor. Overnight deck hammering operations will be winding down on October 24. Over the next two weeks, nighttime operations will consist of beam removal and other activities that do not have the same level of noise impacts.
Travel Impacts
Upcoming ramp closures
The following ramp closures are expected:
- Ramp A (I-95 NB to I-90 EB/WB) and Ramp B (I-90 EB/WB to I-95 NB) from Thursday, October 29, 2026, through Friday, November 6, 2026. Lane reductions on both ramps began on Monday, July 20 and will continue for the next year.
- I-90 EB/WB alternating high-speed/low-speed lane closures from Monday, October 26, 2026 through Friday, November 6, 2026.
- I-95 NB/SB alternating high-speed/low-speed lane closures from Monday, October 26, 2026 through Friday, November 6, 2026.
- Ramp C (I-90 EB/WB to I-95 SB) from Monday, October 26, 2026, through Friday, November 6, 2026.
Over the next two weeks, drivers should anticipate lane closures on the highway, bridges, and on/ off ramps; rolling roadblocks; and intermittent road closures within the work zones listed below.
Scheduled Work
I-90 over I-95 and the Charles River
Work within the project area around the bridge carrying I-90 over I-95 and the Charles River will entail:
- Approach roadway reconstruction
- Demolition of existing westbound structure (day and night shifts)
Work has resumed in the overnight hours from 9:00 p.m. to 4:00 a.m., with additional noise mitigation implemented. - Noise wall foundation installation, along I-90 eastbound and I-90 westbound
- Noise wall panel installation along I-90 eastbound
- Mechanically stabilized earth wall construction along I-90 westbound
- Bridge substructure construction
Ramp G Bridges
Work within the project area around the ramp bridges carrying I-95 north and south to I-90 eastbound will entail:
- Landscape plantings and seeding
- Milling and paving approach ramps
Ramp A/B Over I-95 and the Charles River
Work within the project area around the bridge carrying I-90 ramp traffic over I-95 and the Charles River will entail:
- Demolition of existing bridge deck
- Forming the bridge deck
- Existing bridge deck repairs
- Substructure repairs
Work Hours
- Daytime hours: Monday through Friday from 6:00 a.m. to 8:30 p.m. (Saturday 6:00 a.m. to 8:30 p.m., as required)
- Nighttime hours: Monday through Saturday from 8:30 p.m. to 4:00 a.m., as required
Travel Tips
Drivers should pay attention to all signage and move carefully through the work zone. Police details, lane markings, temporary barriers, traffic cones, signage, and other tools will be used to control traffic and maintain safe work zones.