Overview
Contractor: Constellation NewEnergy, Inc.
Cost: $10,500,000
Annual Cost Savings: $570,000
Annual savings:
- Electricity (kWh) – 3.1 million
- Natural gas (therms) – 23,600
- Water (gallons) – 3.75 million
- CO2 (metric tons) – 1,700
Project goals:
- Make Salem State more energy efficient
- Improve control of lighting, and heating
- Replace aging HVAC equipment
- Improve ice rink efficiency and conditions
Project features
- Lighting upgrades and controls
- Energy management systems
- Domestic hot water heater replacement
- High efficiency gas boiler installation
- New ice rink floor and mechanical systems
- Low-E Ceiling for ice rink