Exelon West Medway Facility, Medway

Two simple-cycle combustion turbine generators are designed to burn natural gas (or ultra low-sulfur distillate) and operate during times of peak electrical energy demand.

Draft Acid Rain Permit

MassDEP in November 2017 issued a draft Acid Rain Permit for the construction of two simple-cycle combustion turbine generators at the Exelon West Medway facility, 9 Summer Street, Medway.

The agency accepted public comment through Friday, December 15, 2017.

Additional Resources

Final Air Permits

MassDEP in December 2016 issued the final Air Quality Comprehensive Plan Approval and Prevention of Significant Deterioration (PSD) Permit for the Exelon West Medway Project.

Additional Resources

Proposed Air Plan Approval & PSD Permit

MassDEP proposed approval of the Exelon West Medway project, subject to conditions and a public comment period that included a public hearing at Medway Middle School and ended in November 2016.