About the Randolph Ave. (Rt. 28)/Chickatawbut intersection improvement project

MassDOT is reconstructing the Randolph Avenue (Route 28) and Chickatawbut Road intersection into a roundabout. Learn more about the project.

Overview

The goal of this project is to address roadway safety, provide accessible pedestrian and bicycle facilities, and improve traffic flow. The project intends to reduce the likelihood of fatal and injury crashes and to continue lowering vehicle speeds in conjunction with the permanent Road Diet. This project will also address non-ADA compliant pedestrian and cyclist accommodations.

Pedestrian and cyclist improvements

Aerial view of proposed work

Improved and accessible pedestrian and bicycle facilities will be provided within the project limits. This will include accessible ramps and a new Shared Use Path.

Construction timeline and impacts

Fall 2026 – Winter 2026

  • Preliminary work: survey, layout, and construction safety signage
  • Pending approvals, demolish building, clearing and grubbing, and partial underground utilities

Spring 2027 – Fall 2027

  • Establish work zones
  • Demolish and construct sidewalks, pedestrian ramps, and curbing
  • Pedestrian signal equipment installation and utility work
  • Full-depth roadway reconstruction

Spring 2028 – Fall 2028

  • Establish work zones
  • Demolish and construct sidewalks, pedestrian ramps, and curbing
  • Pedestrian signal equipment installation and utility work
  • Full-depth roadway reconstruction

Spring 2029 – Fall 2029

  • Construct center island and medians
  • Complete retaining structure
  • Install pedestrian crossing signals and street lighting
  • Final paving, markings, and signage

The project is scheduled to be completed in Spring of 2030.

Work Hours

Work hours are Monday through Friday, 7 a.m. – 3:30 p.m. Nighttime operations are allowed with prior MassDOT approval. Any work that will disrupt travel shall occur outside of peak travel times

For more details, including graphic of construction staging, please visit the documents and meeting materials page.

Final design

Rendering of final design

Background

The intersection of Randolph Ave. (Rt. 28)/Chickatawbut Road ranked 7th out of 200 in the latest listing of most dangerous intersections in the state. There have been 188 vehicle crashes between 2016 and 2022; with 49% being left-turn crashes. A 2016 Road Safety Audit (RSA) identified problems in the intersection and recommended changes to reduce crashes. The RSA, and analysis of alternatives, has led to the proposed solution of a roundabout.

In addition, pedestrian and cyclist accommodations are not ADA-compliant and need improvement.

MassDOT conducted a Road Diet Pilot on Route 28 (Randolph Avenue) from Reedsdale Road to Chickatawbut Road from Fall of 2025 to Spring of 2026. The Road Diet achieved safety goals and was made permanent. Within the corridor, Route 28 now carries one lane in each direction. The roundabout design was updated to adapt to the new roadway configuration and is now a single lane roundabout with single lane approaches.
 

Additional resources

Stay informed

Continue to visit the project website for more information on the project, impacts, and how to get involved and stay informed.

At the bottom of the page, sign up with your email to receive project updates.