Cambridge Courthouse Third Street

The project replaced the existing windows addressed required exterior masonry required repairs, replaced the roof and repaired the cupola and replaced the roof top air handling unit. The detention area was reconfigured to meet the guidelines of the court system as well as provide an accessible holding cell.

Project Details

Cambridge Courthouse, Third Street exterior

Study and Project Designer: HDR Architecture, PC
Contractor:  TRAC Builders, Inc.
Project Type: Design, Bid, Build
Gross Square Feet:  42,000 (approx.)
Est. Project Cost: $7,244,445
Est. Construction Substantial Completion Date: Spring 2025

Project Features

  • Window and roof replacement, masonry, penthouse, parapet, skylight and cupola repairs
  • Detention: sight and sound and accessibility improvements
  • MEP/FP: AHU, roof fans and drain replacement, backflow preventer installation

Notable sustainable design features:

  • The window replacement was the most impactful project component in energy savings going forward. Ventilation energy use and power usage of new Air Handling Unit will also help save energy. New roof insulation meets new energy performance requirements.