Underside of the bridge – May 2025 – End of January 2026
Construction work on the underside (substructure) of the bridge began on May 4, 2025 and will continue through the end of January 2026. The following travel impacts will be implemented:
- Overnight single lane closures on Route 1A Northbound at Callahan Tunnel approach (Sunday through Thursday)
- Overnight closures of the Callahan Tunnel will take place the following nights from 11:00 pm each night to 5:00 am the following morning, with signage and law enforcement to guide drivers through the work area:
- Tuesday, January 20
Project schedule update – project anticipated to be complete by end of January
Based on the scope of repairs, inclement weather, and the need to coordinate with other projects, MassDOT has revised the schedule such that bridge work will now be complete by the end of January 2026. Crews will carry out construction activities on the underside of the bridge during overnight hours on Sunday through Thursday, from 11:00 PM each night to 5:00 AM the following morning, through the end of January. There are no further anticipated construction activities after this date for the Richmond Street Bridge Preservation Project.
Crews have finished all work on the surface of the Richmond Street bridge, with the final fence installation completed on December 31, 2025.
Roadway and sidewalks fully reopened
On the evening of Tuesday, August 26, crews completed paving operations on Richmond Street, allowing the roadway and sidewalks to fully reopen for Full Beneficial Use. This concludes the major roadway work on the surface of the Richmond Street Bridge.
Some minor work, such as fence construction and asphalt sealing, will remain. This work may require occasional sidewalk closures or temporary traffic shifts as needed.
Stage 1 construction – COMPLETE
This stage is complete. Crews carried out various bridge and roadway repairs.
Stage 2 construction - COMPLETE
This stage is complete. Crews carried out various bridge and roadway repairs, sidewalk replacement, and installed new bridge railings.
Construction work hours
Crews will work as follows:
- Monday – Friday, 7 a.m. – 7 p.m. for bridge surface and roadway work
- Sunday – Thursday, 9 p.m. each night – 5:00 a.m. the following morning for concrete repairs on the underside of the bridge