Traffic and construction updates - Cambridge - Alewife Brook Parkway Bridge Superstructure replacement

Construction will require temporary changes to traffic patterns, pedestrian routes, and bicycle access within project area.

Expected impacts include:

  • The sidewalk on the bridge is anticipated to be closed for the duration of the project.
  • The bicycle network under the bridge will be temporarily closed during: 
    • A few periodic weekdays between August 2026 and Fall 2026 to install a temporary utility structure adjacent to the bridge
    • Two non-consecutive weekend construction periods in Spring/Summer 2027 
    • Advance notice of upcoming closures will be distributed and posted online
  • Temporary pedestrian and bicycle detours will be in place during all closures.
  • Access to the MBTA Alewife station and parking garage will be maintained at all times, and MBTA Red Line service will not be impacted. 
  • Periodic single-lane closures on Alewife Brook Parkway will occur as needed during construction.

Initial work activities

  • Installing erosion/sedimentation controls, tree protection, and tree trimming
  • installing temporary shoring
  • Installing temporary utility bridge and temporary gas main
  • Installing overhang brackets
  • Removing and resetting lighting
  • Saw cutting abutments

Project photos

Temporary Pedestrian Detour – All Times (No bicycle detour)

Aerial view of temporary Pedestrian Detour

Temporary Pedestrian Detour – Weekends

Aerial view of temporary Pedestrian Detour – Weekends

Temporary Bicycle Detour – Weekends

Aerial view of temporary Bicycle Detour – Weekends

Temporary Weekend Overnight Vehicle Detour Route

Aerial view of temporary Weekend Overnight Vehicle Detour Route

Temporary Weekend Overnight Truck Detour Route

Aerial view of temporary Weekend Overnight Truck Detour Route