Expected impacts include:
- The sidewalk on the bridge is anticipated to be closed for the duration of the project.
- The bicycle network under the bridge will be temporarily closed during:
- A few periodic weekdays between August 2026 and Fall 2026 to install a temporary utility structure adjacent to the bridge
- Two non-consecutive weekend construction periods in Spring/Summer 2027
- Advance notice of upcoming closures will be distributed and posted online
- Temporary pedestrian and bicycle detours will be in place during all closures.
- Access to the MBTA Alewife station and parking garage will be maintained at all times, and MBTA Red Line service will not be impacted.
- Periodic single-lane closures on Alewife Brook Parkway will occur as needed during construction.
Initial work activities
- Installing erosion/sedimentation controls, tree protection, and tree trimming
- installing temporary shoring
- Installing temporary utility bridge and temporary gas main
- Installing overhang brackets
- Removing and resetting lighting
- Saw cutting abutments
Project photos
Temporary Pedestrian Detour – All Times (No bicycle detour)
Temporary Pedestrian Detour – Weekends
Temporary Bicycle Detour – Weekends
Temporary Weekend Overnight Vehicle Detour Route
Temporary Weekend Overnight Truck Detour Route