Apply for permission to blast at a quarry

If you plan on blasting at a quarry near a gas pipeline, here is how to apply for permission.
You must first get approval at least 5 business days in advance of the blast

Pipeline Safety Division

The Details of Apply for permission to blast at a quarry

What you need for Apply for permission to blast at a quarry

If you intend to blast at a quarry within 500 feet of a natural gas pipeline or metering and regulation station, you must first get approval from the DPU's Pipeline Safety Division at least five business days in advance of the blast.  If you do not get approval before blasting, you may be found in violation of state law, St. 2014, c. 149, sec. 7.

To get the required approval, you must submit an Application for Blasting at Quarries, by email or mail, along with the following:

  • a copy of the blasting plan;
  • the associated Dig Safe ticket(s); and
  • the approved FP‑6 permit issued by the local fire department.

The application is fillable if you use Adobe Reader or Adobe Fill & Sign (for iOS and Android) or you may print and fill out the application by hand.

How to apply Apply for permission to blast at a quarry

You can email your application to the following individuals (include all three email addresses)

Or, you can mail your application and associated documents to:

Director, Pipeline Safety Division
Department of Public Utilities
One South Station
Boston, MA 02110

Next steps for Apply for permission to blast at a quarry

  1. Advance Electronic Notice

    No less than 24 hours before your blasting operation, you must email the following individuals with the scheduled date of the specific blasting operation, a copy of the associated Dig Safe ticket(s), and a copy of the approved Application for Blasting:

  2. Notice of cancelled blast

    If your planned blasting operation does not take place on the scheduled date, you must inform the individuals noted above by email.

More info about Apply for permission to blast at a quarry

You will need to submit a new Application if the following occurs:

  • If your schedule changes and the blast will occur on a date other than the one specified in your Application, you must submit a new Application with a copy of the blasting plan, the associated Dig Safe ticket(s), and the approved FP-6 permit. 
  • If your blasting plan changes, you must submit a new Application (with the associated Dig Safe ticket(s) and FP-6 permit).  You must also secure a new Dig Safe ticket by calling 811 or (888) 344-7233.

Contact for Apply for permission to blast at a quarry

Address
One South Station, 5th Floor, Boston, MA 02110

Feedback

Did you find what you were looking for on this webpage? * required
We use your feedback to help us improve this site but we are not able to respond directly. Please do not include personal or contact information. If you need a response, please locate the contact information elsewhere on this page or in the footer.
We use your feedback to help us improve this site but we are not able to respond directly. Please do not include personal or contact information. If you need a response, please locate the contact information elsewhere on this page or in the footer.

If you need to report child abuse, any other kind of abuse, or need urgent assistance, please click here.

Feedback