About the project
The goals of the Needham/Newton Corridor Roadway Improvements Project are to improve:
- Traffic safety and operations
- Transit operations
- Multimodal accommodations
Improvements will include the following:
- Roadway widening, full depth construction, and mill and overlay
- Raised bike lane and sidewalk installation
- Shared Use Path for bikes and pedestrians
- Traffic signal replacements – 5 locations
- New traffic signal installation – 2 locations
- Installation of stormwater basin and infiltration trenches
Schedule
Notice to Proceed – summer 2020
Construction Start – fall 2020
Construction Complete – 2025