MassDOT is redesigning and reconstructing Route 20 in Charlton and Oxford to improve safety and traffic operations. Changes may include:
- Roadway widening
- Introduction of sidewalks and shared use paths
- Implementation of a median barrier separating opposing directions of travel
- Enhanced traffic operations at intersections
- Replacement of bridges over the Little River in Charlton and the French River in Oxford
- Installation of a roundabout at the intersection of Route 20 and Oxbow Road
- Introduction of Best Management Practices to enhance stormwater treatment
The design will include:
- Bicycle and pedestrian accommodations
- Signage
- Pavement markings
- Guardrail
- Retaining walls
- Storm drainage
- Overhead and underground utility relocations
MassDOT has selected a Design-Builder Team, D.W. White Construction Inc. and TranSystems, who will handle both the design and construction. This reduces the time needed to complete the project and promotes collaboration among the engineers, contractor, and MassDOT staff.
Next Steps
- Design-Builder to complete final roadway design
- Continue pre-construction activities: supplemental borings and test pits, clearing and grubbing and utility relocations
- Continue public outreach at key milestones
Milestone | Anticipated Date |
---|---|
Final design complete | Summer 2023 |
Significant construction begins (anticipated) | March 2024 |
Substantial completion (anticipated) | September 2026 |
Project completion | November 2026 |