Expected timeline
Stage 1A: September 2025 – May 2026
Stage 1B: May 2026 – Fall 2026
Stage 2A: Fall 2026 – Spring 2027
Lanes on I-90 are expected to be restored for travel at 5:00 a.m. and close at approximately 10:00 p.m.
Stage 2B: Spring 2027 – Fall 2027
Stage 3A: Fall 2027 – Spring 2028
Lanes on I-90 are expected to be restored for travel at 5:00 a.m. and close at approximately 10:00 p.m.
Stage 3B: Spring 2028 – Fall 2028
Lanes on I-90 are expected to be restored for travel at 5:00 a.m. and close at approximately 10:00 p.m.
Stage 4: January 2029 – December 2029 – final completion
Stay informed
Continue to visit the project website for more information on the project, impacts, and how to get involved and stay informed. To receive project updates, attend public information meetings, and get more information on the project, we invite you to sign up for the project’s e-list to receive meeting notifications and project updates.