These Division of Capital Asset Management and Maintenance (DCAMM) projects are for Design/Bid/Build construction under MGL C. 149 - and typically are under $20M, most will be under $10M. Prior to the general contractor bids, there will be Filed Sub-Bids for work in the relevant categories of the s.44F- Categories of Work.
Projects in Design - estimated design by quarter
| Project # | Project Name | City | Total Project Cost | 2026 Q4 (Oct. - Dec.) | 2027 Q1 (Jan. - March) | 2027 Q2 (Apr. - June) | 2027 Q3 (Jul. - Sep.) |
|---|---|---|---|---|---|---|---|
| DCP2702 | Hurley Building - Emergency Generator Replacement | Boston | $0.65 Mil | X | |||
| DCP2706 | MITC Building - Elevator Machine Room Exhaust & MEP Cooling Study | Chelsea | $0.50 Mil | X | |||
| DCP2708 | Springfield Data Center - BMS Emergency Repairs | Springfield | $0.05 Mil | X | |||
| DCP2717 | Hurley Building - Steam Heating | Boston | $0.52 Mil | X | |||
| DPH2601 | Tewksbury Hospital Saunders Building - Roof Replacement Phase II | Tewksbury | $12.56 Mil | X | |||
| F2026A100 | Dorchester Armory Renovation | Dorchester | $1.06 Mil | X | |||
| NAC2601 | Applied Learning Space Modernization | North Adams | $0.50 Mil | X | |||
| RCC2601 | Applied Learning Space Modernization | Roxbury | $0.50 Mil | X | |||
| TRC2503 | Fenton Judicial Center - Renovations | Lawrence | $0.80 Mil | X |
Projects Going to Bid - estimated bid by quarter
| Project # | Project Name | City | Total Project Cost | 2026 Q4 (Oct. - Dec.) | 2027 Q1 (Jan. - March) | 2027 Q2 (Apr. - June) | 2027 Q3 (Jul. - Sep.) |
|---|---|---|---|---|---|---|---|
| DCP2143 | Lindemann - Electrical Infrastructure Assessment | Boston | $3.82 Mil | X | |||
| DCP2423 | MITC - OSD Print Shop | Chelsea | $3.03 Mil | X | |||
| DCP2702 | Hurley Building - Emergency Generator Replacement | Boston | $0.65 Mil | X | |||
| DCP2708 | Springfield Data Center - BMS Emergency Repairs | Springfield | $0.05 Mil | X | |||
| DCP2717 | Hurley Building - Steam Heating | Boston | $0.52 Mil | X | |||
| DMH2601 | Solomon Carter Fuller - Absorption Chiller Replacement | Boston | $4.52 Mil | X | |||
| DPH2601 | Tewksbury Hospital Saunders Building - Roof Replacement Phase II | Tewksbury | $12.56 Mil | X | |||
| TRC2304 | East Boston Courthouse - Separation | East Boston | $0.26 Mil | X | |||
| TRC2502 | Trial Courts Physical Security Hardware Upgrades | $12.50 Mil | X | ||||
| TRC2503 | Fenton Judicial Center - Renovations | Lawrence | $0.80 Mil | X |
Project Start Dates - estimated construction start by quarter
| Project # | Project Name | City | Total Project Cost | 2026 Q4 (Oct. - Dec.) | 2027 Q1 (Jan. - March) | 2027 Q2 (Apr. - June) | 2027 Q3 (Jul. - Sep.) |
|---|---|---|---|---|---|---|---|
| BSB2403 | State House Dome Rehabilitation & Repair | Boston | $16.95 Mil | X | |||
| DCP2423 | MITC - OSD Print Shop | Chelsea | $3.03 Mil | X | |||
| DCP2607 | McCormack Building - Air Handler Units Rehabilitation | Boston | $3.90 Mil | X | |||
| DCP2702 | Hurley Building - Emergency Generator Replacement | Boston | $0.65 Mil | X | |||
| DCP2708 | Springfield Data Center - BMS Emergency Repairs | Springfield | $0.05 Mil | X | |||
| DCP2717 | Hurley Building - Steam Heating | Boston | $0.52 Mil | X | |||
| DMH2601 | Solomon Carter Fuller - Absorption Chiller Replacement | Boston | $4.52 Mil | X | |||
| DMH2602 | Solomon Carter Fuller - Emergency Steam Heat and Hot Water Refurbishing | Boston | $2.48 Mil | X | |||
| DPH2601 | Tewksbury Hospital Saunders Building - Roof Replacement Phase II | Tewksbury | $12.56 Mil | X | |||
| EPS2401 | North Shore Regional 911 Call Center Water leaks | Middleton | $1.20 Mil | X | |||
| TRC2304 | East Boston Courthouse - Separation | East Boston | $0.26 Mil | X | |||
| TRC2502 | Trial Courts Physical Security Hardware Upgrades | $12.50 Mil | X | ||||
| TRC2503 | Fenton Judicial Center - Renovations | Lawrence | $0.80 Mil | X | X | ||
| X25C149DC | State Transportation Building Roof and Cooling Towers Replacement | Boston | $5.60 Mil | X |
Information provided on this page was effective 10/31/2026 and is subject to change.