Construction activities are anticipated to start in Spring 2026. Weather and unexpected circumstances make all construction activities subject to change without notice, but we will do our best to keep you updated. This page will be updated with the latest available construction information.
Fall 2026
What's New?
- This fall, September through November 2026, the contractor anticipates the following construction activities throughout the Route 114 corridor:
- Demolition activities will continue at properties located at the intersection of Route 114 and Hillside Road in North Andover, including asbestos abatement, utility work, and demolition of structures at 582, 591, 599, and 607 Turnpike Street.
- Excavation and gravel placement are underway between the Andover Bypass and Willow Street for the future shared-use path.
- Route 114 center median removal and temporary paving activities are underway throughout the corridor to facilitate traffic movements around active work zones.
- Installation and maintenance of erosion control, sediment control, and stormwater protection measures in advance of and alongside upcoming work activities.
- Test pitting (soil sampling and utility investigation) at various locations on Route 114 throughout the corridor will continue through September.
- Utility coordination and field verification activities will continue, including confirmation of existing utility locations in advance of future utility work. Activities will include:
- Sawcutting of roadway surfaces
- Utility pole relocation work
- Gas utility relocation work
When is this Work Happening?
- Work activities are scheduled on weekdays, Monday through Friday, during the fall construction season.
- Work hours are from 7:00 a.m. to 3:00 p.m.
How Will this Affect You?
- Lane shifts, traffic control devices, and police details may be required on Route 114 in the project limits to support these activities for public and worker safety.
- Construction signage will remain in place and may be adjusted as needed to support shifting work areas and maintain safe travel through the corridor.
- Access for pedestrians and emergency services will be maintained.
- Drivers traveling through the affected areas should expect delays, reduce speed, and use caution.