Project details
This project will deliver a safer and more efficient intersection at Route 28 (Fellsway/McGrath Highway) and Route 38 (Mystic Avenue) in Somerville. Key improvements include a southbound lane drop on McGrath Highway at Broadway to reduce driver conflict points and improve safety. Modern adaptive signal systems will improve real-time traffic flow based on actual conditions. The project also features new pedestrian crossings, widened sidewalks, separated bike lanes, and upgraded curb ramps to enhance accessibility and mobility for all users.
Benefits of the project include increased safety for all users, more predictable traffic patterns with adaptive signals, and support for multi-modal transportation.
What you need to know
Work hours
Standard work hours will be Monday through Friday from 9:00 AM to 3:00 PM. Occasional night or weekend work may be required for final paving and line striping. Advance notice will be provided for any off-hour construction activity.
- No permanent lane closures during peak hours.
- Temporary daytime lane closures during construction periods.
- Pedestrian detours will remain in place 24/7 where sidewalk work is underway.
- Overnight lane closures expected during final paving and line striping in Summer/Fall 2027.
Construction timeline and activities
- Spring/Summer 2025: Project-Wide Work: Drainage, Utilities, and Concrete Foundations for Traffic Signals.
- Fall 2025: Fellsway (North of Mystic/McGrath Intersection): Curb relocation, new sidewalks, and bike lanes.
- Winter 2025–2026: Winter Shutdown (December 2025 to March 2026).
- Spring/Summer 2026: McGrath Highway NB & SB (Broadway to Mystic Ave): Curb relocation, new sidewalks, and bike lanes.
- Summer 2026: Mystic Ave NB & SB (Wheatland to McGrath): Curb relocation, new sidewalks, and bike lanes.
- Fall 2026: McGrath/Mystic Avenue Intersection: Curb relocation, new sidewalks, and bike lanes.
- Winter 2026–2027: Winter Shutdown (December 2026 to March 2027).
- Spring 2027: McGrath Hwy/Mystic Avenue Intersection: Continued sidewalk and bike lane work.
- Summer/Fall 2027: Project-Wide Night Work: Final paving and line striping from 9:00 PM to 5:00 AM.
- September 2027: Project Completion.