Christian A. Herter Park Master Plan

Last updated: 6/24/2022

View information about the September 28, 2022 Public Meeting.  

View the Herter Park Master Plan at DCR Master Plans 

herter park

Background

Designated as Christian A. Herter Park in 1974, this area of the Charles River Reservation was first developed as the Speedway in 1899. Designed by Charles Eliot, the Speedway featured a 1.75-mile parkway, a 1-mile racetrack for harness racing and bicycles and a pedestrian promenade. In 1928, Soldiers Field Road was a tree-lined two-lane parkway (one eastbound, one westbound) with car parking on the Speedway side. The Speedway was in use until at least 1951, but since few people had horses and carriages by that time, it was soon incorporated into Soldiers Field Road. The park was redesigned in 1958-1960 to house the Metropolitan Boston Arts Center, but the facility was short-lived. After use as the Publick Theater, ICA and Sports Museum, the Herter Center has been vacant.

Project Goals and Scope

The 60-acre project area extends from Arsenal Street Bridge to below Eliot Bridge. DCR’s vision for Christian A. Herter Park is a dynamic and accessible 4-season facility set in a rich and diverse riverine habitat. The Master Plan process is analyzing and making recommendations for improved circulation and accessibility, stormwater management and green infrastructure, utility infrastructure, and programming—specifically for the Theater and Herter Center. DCR wants an integrated layout for parking, recreation programs and special events to enhance visitor experience, reduce routine maintenance and improve ecosystem function. The project is being coordinated with the Charles River Vegetation Management Plan (CRVMP) and DCR’s 2022 Stormwater Handbook.

 

Public Outreach

  • Working Group Meeting #1: 3/31/2021
  • Stakeholder Meeting #1: 5/18/2021
  • Public Outreach Meeting #1: 6/10/2021
  • Working Group Meeting #2: 9/13/2021
  • Stakeholder Meeting #2: 9/15/2021
  • Public Outreach Meeting #2: 9/23/2021
  • Friends of Herter Park (Theater) Site Meeting: 10/15/2021
  • Herter Park Community Garden, Charles River Community Garden and Pollinator Network Site Meetings: 11/1/2021, 12/1/2021, 12/2/2021, 3/24/2022.

Project Schedule

3 phases over the course of 12 months:

  • Phase 1: Site Inventory and Analysis; complete July 2021.
  • Phase 2: Master Plan; submittal June 2022; complete September 2022.
  • Phase 3: Landscape Management Plan; submittal June 2022; complete September 2022.

Funding

  • Special Events Trust
  • Design: Halvorson Tighe & Bond, Contract Value:              $ 378,170.50
  • Construction:                                                                                N/A

Project Tracker

 

Item

Date:

Comments

 

Contract: P20-3379-D1A

 

 

 

Notice to Proceed

1/5/2020

 

 

Contract End Date

9/30/2022

 

 

Phase 1: Site Inventory and Analysis

1

Site Walks w/ DCR Project Team

1/22, 2/26, 5/10

complete

2

Information Gathering

Spring 2021

3

Existing Conditions Plan

Spring 2021

4

Site Analysis Plan and Report

June 2021

5

Public Outreach:

  • Working Group Meeting
  • Stakeholder Meeting
  • Public Presentation #1

 

3/31/2021

5/18/2021

6/10/2021

 

6

Site Inventory and Analysis Submittal

July 2021

 

Phase 2: Master Plan

1

Draft Master Plan

  • Design and layout of integrated program elements
  • Utility systems layouts
  • Site Furnishings, materials and signage
  • Special Events programming and overlay diagrams
  • Stormwater management

Est of probable construction cost for each phase

Summer 2021 to

September 2022

 

2

Public Outreach

  • Legislative Meeting
  • Working Group Meeting
  • Stakeholder Meeting
  • Public Presentation #2
  • Amphitheater Working Group
  • Community Gardens Listening Session
  • Community Gardens Working Group Meetings
  • Pollinator Network

9/13/2021

9/15/2021

9/23/2021

9/29/2021

10/15/2021

11/1/2021

12/1, 12/2/2021

3/24/2022

 

complete

3

Final Master Plan

9/2022

 

 

Phase 3: Landscape Management Plan

1

Meet with Project Team

11/2021

 

2

Revise LMP according to DCR direction

Summer 2022

 

3

Project Close Out

9/2022

 