Pre-filing Consultation and Engagement

This Pre-filing Consultation and Engagement page provides information on pre-filing for the siting and permitting of large energy infrastructure facility projects seeking approval from the Energy Facilities Siting Board (EFSB).

Overview

In November 2024, Governor Maura Healey signed into law An Act promoting a clean energy grid, advancing equity and protecting ratepayers, St. 2024 c.239 (the "2024 Climate Act").  The law established changes to the siting and permitting of large clean energy infrastructure in Massachusetts, including new requirements for stakeholder and community engagement before a project application is filed with the Energy Facilities Siting Board (EFSB). 

The Pre-filing Consultation and Engagement Requirements for large energy infrastructure facilities seeking a consolidated permit are established in 980 CMR 16.00. These regulations went into effect on February 27, 2026, and apply to applications filed with the EFSB on or after July 1, 2026. The Department's Division of Public Participation (DPP) oversees the pre-filing consultation and engagement process. 

The new regulations provide opportunities for local government, state agencies, community members, and other stakeholders to learn about and provide input on proposed projects early in the development process to inform project design before applicants file an application with the EFSB.

Project applicants, community groups, and other stakeholders can schedule a 30- or 60-minute DPP Consultation meeting to ask general questions, clarify pre-filing requirements or discuss a specific proposed project currently in the pre-filing process. 

For pre-filing questions, please contact DPP at efsb.prefiling@mass.gov 

Pre-filing Consultation and Engagement Regulations

The full list of final regulations for consolidated permit applications for large clean energy infrastructure facilities can be found on the EFSB Permitting Dashboard. 

Summary of Pre-filing Consultation and Engagement Requirements

During pre-filing, applicants must employ substantial, good faith efforts to inform and involve relevant state and local government agencies, Key Stakeholders, and members of the community about the proposed project and consider feedback received. 

During pre-filing, applicants are required to:

  • Create an account in the Massachusetts Energy Siting Hub (MESH) portal to begin the siting and permitting process.  The MESH portal will serve as a centralized filing and information hub for project applicants, state agencies, local governments, and the public to track the status of projects starting with the pre-filing phase. 
  • Meet with the Division of Public Participation (DPP) and the Office of Environmental Justice & Equity (OEJE) at the Executive Office of Energy and Environmental Affairs (EEA). 
  • Meet with relevant Key Stakeholders such as public interest groups, organizations serving the local community where the proposed project is located, abutters including residents and businesses, community-based organizations, elected or appointed municipal officials, regional planning officials, representatives of labor groups, and Tribes. 
  • Consult with the Massachusetts Environmental Policy Act Office (MEPA) and relevant local government and state agencies to get their input on compliance with regulatory and permitting requirements. 
  • Hold at least two public meetings with members of the community.  Ensure translation and interpretation are provided as per EFSB's Language Access Plan (LAP) and the Languages Spoken in Massachusetts map if the proposed project is located in a community where there are Limited English Proficient (LEP) individuals.
  • Submit the Pre-filing Engagement Status Checklist approximately mid-way through pre-filing.  Submit the Pre-filing Engagement Completion Checklist and Pre-filing Notice at the end once the pre-filing consultation and engagement requirements have been met. 

The Guide to Pre-filing Consultation and Engagement Requirements (coming soon) provides more information on the pre-filing process and templates that the applicant should use to provide information on the proposed project to DPP.

Public Participation During Pre-filing

Pre-filing gives community members and Key Stakeholders early opportunities to learn about the proposed project, share their perspectives, provide input, and understand how that input is considered before an application is filed with the EFSB.

Applicants are required to summarize comments received during one-on-one and public meetings and any modifications in project design made in response to those comments.  The summary submitted to DPP during pre-filing is part of the public record and can be used by the EFSB to support its decision-making process. 

Schedule a Pre-filing Consultation Meeting

Project applicants, local governments, community-based organizations, and other interested stakeholders can schedule a meeting with DPP to discuss the Pre-filing Consultation and Engagement Requirements and any specific aspects of a proposed project in pre-filing. 

Important Dates

ActionDate
Final Regulations Published in Mass. RegisterFebruary 27, 2026
Statutory Deadline to Promulgate RegulationsMarch 1, 2026
Additional Stakeholder Engagement on ImplementationFrom March 1, 2026
Implementation of New Consolidated Permit ProgramJuly 1, 2026

Resources for Project Applicants, Key Stakeholders, and Community