Decisions
Docket Number | Company | Description | Location |
---|---|---|---|
EFSB 22-02 | Medway Grid, LLC | Petition of Medway Grid, LLC for Approval to Construct a Battery Energy Storage System Pursuant to G.L. c. 164, § 69J⅟4, in Medway, Massachusetts Issued on: 5/11/23 | Medway |
EFSB 21-02 | Cranberry Point Energy Storage, LLC | Petition of Cranberry Point Energy Storage, LLC Pursuant to G.L. c. 164, § 69J ¼ for Approval to Construct and Operate a 150 MW Battery Energy Storage System in Carver, Massachusetts Issued on 5/11/23 | Carver |
EFSB 17-04 | Milford Power, LLC | Milford Power, LLC Notice of Project Change Issued on: 10/1/18 | Milford |
EFSB 17-01 | Exelon West Medway, LLC and Exelon West Medway II, LLC | In the Matter of the Initial Petition and Application of Exelon West Medway, LLC and Exelon West Medway II, LLC for a Certificate of Environmental Impact and Public Interest Issued on: 8/4/17 | Medway |
EFSB 15-1A/D.P.U. 15-25A | Exelon West Medway, LLC and Exelon West Medway II, LLC | Exelon West Medway, LLC and Exelon West Medway II, LLC, Notice of Project Change Issued on: 8/4/17 | Medway |
EFSB 15-06/D.P.U. 15-180 | NRG Canal 3 Development LLC | Petition of NRG Canal 3 Development LLC to Construct a New Generating Facility in the Town of Sandwich Pursuant to G.L. c. 164, § 69J¼ Petition of NRG Canal 3 Development LLC for Exemptions from the Zoning Bylaw of the Town of Sandwich Pursuant to G.L. c. 40A, § 3 Issued on: 7/5/17 | Sandwich |
EFFB 07-7/D.P.U. 07-58/07-59 | Brockton Power Company, LLC | Petition of Brockton Power Company, LLC for Approval to Construct a 350 MW Combined Cycle Power Plant in the City of Brockton, Massachusetts and for Zoning Exemptions from the Bylaws of the City of Brockton and for Approval to Construct an Electric Transmission Line in the City of Brockton Issued on: 2/27/17 | Brockton |
EFSB 15-01/D.P.U. 15-25 | Exelon West Medway, LLC and Exelon West Medway II, LLC | Petition of Exelon West Medway, LLC and Exelon West Medway II, LLC to Construct a New Generating Facility in the Town of Medway Pursuant to G.L. c. 164, § 69J¼ Petition of Exelon West Medway, LLC and Exelon West Medway II, LLC for Exemptions from the Zoning Bylaw of the Town of Medway Pursuant to G.L. c. 40A, § 3 Issued on: 11/18/16 | Medway |
EFSB07-7/DPU07-58/07-59 | Brockton Power Company, LLC | Petition of Brockton Power Company, LLC for Approval to Construct a 350 MW Combined Cycle Power Plant in the City of Brockton, Massachusetts and for Zoning Exemptions from the Bylaws of the City of Brockton and for Approval to Construct an Electric Transmission Line in the City of Brockton Issued on: 8/6/16 | Brockton |
EFSB 13-1 | Footprint Power Salem Harbor Development LP | In the Matter of the Initial Petition and Application of Footprint Power Salem Harbor Development LP for a Certificate of Environmental Impact and Public Interest Issued on: 2/25/14 | Salem |
EFSB 12-2 | Footprint Power Salem Harbor Development LP | In the Matter of the Petition of Footprint Power Salem Harbor Development LP for Approval to Construct a Bulk Generating Facility in the City of Salem, Massachusetts Issued on: 10/10/13 | Salem |
EFSB 99-4C | GenOn Kendall, LLC | GenOn Kendall, LLC Notice of Project Change Issued on: 1/9/12 | Cambridge |
EFSB 07-7A/07-58/59 | Brockton Power Company, LLC | In the Matter of Brockton Power Company LLC Project Change Filing Issued on: 9/28/11 | Brockton |
EFSB 08-1 | Westfield Land Development Company, LLC | In the Matter of the Petition of Pioneer Valley Energy Center, LLC for Approval to Construct a Generating Facility in the City of Westfield, Massachusetts and the Petition of Pioneer Valley Energy Center, LLC and Westfield Gas & Electric for Approval to Construct a Natural Gas Pipeline in the City of Westfield, Massachusetts Issued on: 10/19/09 | Westfield |
EFSB07-7/DPU07-58/07-59 | Brockton Power Company, LLC | In the Matter of the Petition of Brockton Power Company, LLC for Approval to Construct a 350 MW Combined Cycle Power Plant in the City of Brockton, Massachusetts and for Zoning Exemptions from the Bylaws of the City of Brockton and for Approval to Construct an Electric Transmission Line in the City of Brockton Issued on: 8/7/09 | Brockton |
EFSB 07-2 | Montgomery Energy Billerica Power Partners, L.P. | In the Matter of the Petition of Montgomery Energy Billerica Power Partners, LP for Approval to Construct a 348 MW Peaking Power Generation Facility in the Town of Billerica, Massachusetts Issued on: 3/3/09 | Billerica |
EFSB 07-6 | Mass Municipal Wholesale Electric Company (MMWEC) | In the Matter of the Petition of Massachusetts Municipal Wholesale Electric Company For Approval To Construct a Bulk Generating Facility in the Town of Ludlow, Massachusetts Issued on: 12/12/08 | Ludlow |
EFSB 07-1/DTE 07-5 | Braintree Electric Light Department | In the Matter of Braintree Electric Light Department Petition For Approval To Construct a 116 Megawatt Single-Cycle Generating Facility and For a Zoning Exemption from the Bylaws of the Town of Braintree Issued on: 2/29/08 | Braintree |
EFSB 98-7C | Sithe Edgar | In the Matter of the Petition of Fore River Development, LLC for Approval to Construct a Bulk Generating Facility in the Town of Weymouth, Massachusetts Issued on: 9/18/06 | Weymouth |
EFSB 98-7B | Sithe Edgar | Motion for Extension of Time to Commence Noise Monitoring at the Fore River Generating Facility in Weymouth, Massachusetts Issued on: 3/3/04 | Weymouth |
EFSB 97-5 EFSB 01-1 | IDC | Motion to Withdraw the Petition of IDC Bellingham LLC, for Approval to Construct and Operate a 700-MW Bulk Generation Facility inBellingham, Massachusetts and the Application of IDC Bellingham LLC for a Certificate of Environmental Impact and Public Interest Issued on: 11/13/03 | Bellingham |
EFSB 99-4B | Mirant Kendall LLC | Notice of Project Change - Realignment of Broad Canal Walkway Design Issued on: 10/9/08 | Cambridge |
EFSB 99-1A | Brockton Power | In the Matter of the Petition of Brockton Power, LLC for Approval to Construct a Bulk Generating Facility in the City of Brockton, Massachusetts Issued on: 8/18/03 | Brockton |
EFSB 99-4A | Mirant Kendall, LLC | Southern Energy Kendall, LLC Motion for Further Extension to Comply with Condition E Issued on: 7/14/03 | Cambridge |
EFSB 99-4A | Mirant Kendall | Southern Energy Kendall, LLC Motion for Further Extension to Comply with Condition E Issued on: 6/13/03 | Cambridge |
EFSB 99-4A | Mirant Kendall, LLC | Southern Energy Kendall, LLC Motion for Further Extension to Comply with Condition E Issued on: 5/22/03 | Cambridge |
EFSB 98-7A | Sithe Edgar | Sithe Edgar Development LLC Notice of Probable Violations Issued on: 4/17/03 | Weymouth |
EFSB 98-10 | Sithe West Medway | Sithe West Medway Development LLC Motion for Extension of Approval of Petition Issued on: 4/10/03 | Medway |
EFSB 99-4A | Mirant Kendall, LLC | GenON Kendall, LLC Notice of Project Change Issued on: 3/10/03 | Cambridge |
EFSB 99-1 | Brockton Power, LLC | Brockton Power, LLC, Motion for Extension of Approval of Petition Issued on: 3/10/03 | Brockton |
EFSB 99-4A | Mirant Kendall | Petition of Southern Energy Kendall, LLC for Approval to Upgrade and Replace Generating Facilities at the Existing Kendall Square Station in Cambridge, Massachusetts Issued on: 11/15/02 | Cambridge |
EFSB 98-7A | Sithe Edgar | Sithe Edgar Development LLC Notice of Probable Violations Issued on: 7/31/02 | Weymouth |
EFSB 98-8A | Sithe Mystic | In the Matter of the Petition of Sithe Mystic Development LLC for Approval to Construct a Bulk Generating Facility in the City of Everett, Massachusetts Issued on: 11/30/01 | Everett |
EFSB 98-7A | Sithe Edgar | In the Matter of the Petition of Sithe Edgar Development LLC for Approval to Construct a Bulk Generating Facility in the Town of Weymouth, Massachusetts Issued on: 11/30/01 | Weymouth |
EFSB 01-1 | IDC Bellingham LLC | In the Matter of the Petition and Application of IDC Bellingham LLC for a Certificate of Environmental Impact and Public Interest Issued on: 10/21/01 | Bellingham |
EFSB 97-5B | IDC Bellingham LLC | In the Matter of the Petition of IDC Bellingham LLC, for Approval to Construct and Operate a 525-MW Bulk Generation Facility in the Town of Bellingham, Massachusetts Issued on: 9/25/01 | Bellingham |
EFSB 99-4 | Mirant Kendall | Petition of Southern Energy Kendall, LLC for Approval to Upgrade and Replace Generating Facilities at the Existing Kendall Square Station in Cambridge, Massachusetts Issued on: 8/31/01 | Cambridge |
EFSB 99-3 | Nickel Hill Energy | In the Matter of the Petition of Nickel Hill Energy, LLC, for Approval to Construct a Bulk Generating Facility in the Town of Dracut, Massachusetts Issued on: 8/01 | Dracut |
EFSB 98-9 | Mirant Canal | In the Matter of the Petition of Southern Energy Canal II, LLC. for Approval to Construct a Bulk Generating Facility in the Town of Sandwich, Massachusetts Issued on: 6/15/01 | Sandwich |
EFSB 99-4 | Mirant Kendall | Petition of Southern Energy Kendall, LLC for Approval to Upgrade and Replace Generating Facilities at the Existing Kendall Square Station in Cambridge, Massachusetts Issued on: 2/16/01 | Cambridge |
EFSB 99-4 | Mirant Kendall | Petition of Southern Energy Kendall, LLC for Approval to Upgrade and Replace Generating Facilities at the Existing Kendall Square Station in Cambridge, Massachusetts Issued on: 12/15/00 | Cambridge |
EFSB 99-3 | Nickel Hill Energy | In the Matter of the Petition of Nickel Hill Energy, LLC, for Approval to Construct a Bulk Generating Facility in the Town of Dracut, Massachusetts Issued on: 11/13/00 | Dracut |
EFSB 97-5A | IDC | In the Matter of the Petition of IDC Bellingham LLC, for Approval to Construct and Operate a 525-MW Bulk Generation Facility in the Town of Bellingham, Massachusetts Issued on: 9/12/00 | Bellingham |
EFSB 98-10 | Sithe West Medway | Petition of Sithe West Medway Development LLC for Approval to Construct a Bulk Generating Facility in the Town of Medway, Massachusetts Issued on: 4/13/00 | Medway |
EFSB 99-1 | Brockton Power | Petition of Brockton Power, LLC for Approval to Construct a Bulk Generating Facility in the City of Brockton, Massachusetts Issued on: 3/13/00 | Brockton |
EFSB 98-7 | Sithe Edgar | Petition of Sithe Edgar Development LLC for Approval to Construct a Bulk Generating Facility the Town of Weymouth, Massachusetts Issued on: 2/11/00 | Weymouth |
EFSB 97-5 | Infrastructure Development Corp. (IDC) | Petition of IDC Bellingham, LLC, for Approval to Construct and Operate a 700-MW Bulk Generation Facility in the Town of Bellingham, Massachusetts Issued on:12/21/99 | Bellingham |
EFSB 97-1 | ANP | Petition of ANP Bellingham Energy Company for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 10/18/99 | Bellingham |
EFSB 98-8 | Sithe Mystic | Petition of Sithe Mystic Development LLC for Approval to Construct a Bulk Generating Facility in the City of Everett, Massachusetts Issued on: 9/30/99 | Everett |
EFSB 98-6 | Berkshire Power Development, Inc. | Petition and Application of Berkshire Power Development, Inc. for a Certificate of Environmental Impact and Public Interest Issued on: 9/3/99 | Agawam |
EFSB 97-2 | ANP | Petition of ANP Blackstone Energy Company for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 5/17/99 | Blackstone |
EFSB 97-2 | American National Power (ANP) | Petition of ANP Blackstone Energy Company for Approval to Construct a Bulk Generation Facility and Ancillary Facilities in Blackstone, Massachusetts Issued on: 1/14/99 | Blackstone |
EFSB 91-101A | Cabot Power | Petition of Cabot Power Corporation for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 10/9/98 | Everett |
EFSB 97-1 | ANP | Petition of ANP Bellingham Energy Company for Approval to Construct a Bulk Generation Facility and Ancillary Facilities in Bellingham, Massachusetts Issued on: 8/18/98 | Bellingham |
EFSB 96-4 | U.S. Generating | Petition of U.S. Generating Company for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 5/20/98 | Charlton |
EFSB 95-1 | Berkshire Power | Petition of Berkshire Power Development, Inc. for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 12/22/97 | Agawam |
EFSB 96-4 | U.S. Generating | Petition of U.S. Generating Company for Approval to Construct a Bulk Generation Facility and Ancillary Facilities in Charlton, Massachusetts Issued on: 11/3/97 | Charlton |
EFSB 96-3 | Dighton Power Associates | Petition of Dighton Power Associates for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 7/8/97 | Dighton |
EFSB 91-100 | SEC | Petition of Silver City Energy Limited Partnership for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 8/22/96 | Taunton |
EFSB 91-102A | Altresco Lynn | Petition of Altresco Lynn, Inc. for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 8/16/96 | Lynn |
EFSB 95-1 | Berkshire Power | Petition of Berkshire Power Development, Inc. for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 6/19/96 | Agawam |
EFSB 90-100R2 | Eastern | Petition of Eastern Energy Corporation for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 3/29/96 | New Bedford |
EFSB 91-102A | Altresco Lynn | Petition of Altresco Lynn, Inc. for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 8/17/95 | Lynn |
EFSB 90-100R2 | Eastern (Remand) | Petition of Eastern Energy Corporation for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 6/27/95 | New Bedford |
EFSB 91-100 | Silver City Energy Limited Partnership (SEC) | Petition of Silver City Energy Limited Partnership to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 6/15/94 | Taunton |
EFSB 91-101 | Cabot Power Corporation | Petition of Cabot Power Corporation Issued on: 3/9/94 | Everett |
EFSB 91-102 | Altresco Lynn, Inc. | Petition of Altresco Lynn, Inc. for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 12/15/93 | Lynn |
EFSB 90-100R | Eastern (Remand) | Petition of Eastern Energy Corporation Issued on: 10/27/93 | New Bedford |
EFSB 90-12 90-12A | Boston Edison Company (Phase II) | Petitions of Boston Edison Company for Approval of Its 1990 Long Range Forecast of Electric Requirements and Resources and for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 8/5/93 | Weymouth |
EFSB 90-100A | Eastern | Petition of Eastern Energy Corporation Issued on: 7/30/92 | New Bedford |
EFSB 90-12 90-12A | Boston Edison Company (Phase I) | Petitions of Boston Edison Company for Approval of Its 1990 Long Range Forecast of Electric Requirements and Resources and for Approval to Construct a Bulk Generating Facility and Ancillary Facilities Issued on: 4/10/92 | Weymouth |
EFSB 90-100 | Eastern Energy Corporation (Eastern) | Petition of Eastern Energy Corporation Issued on: 8/2/91 | New Bedford |